DK424 Installation
Cabinet Floor Mounting
7. For systems with just three cabinets, secure the floor fixtures (already attached to the bottom
cabinet) to the floor with the customer-provided floor bolts.
8. Refer to the following sub-sections and anchor the system to concrete, wood, or computer
room floor. After completing those steps, proceed to Step 12. For systems with four or more
cabinets, skip this step and proceed to Step 9.
9. Add remaining cabinets, making sure that the cabinets are connected together at points A and
B with the screws provided.
10. For systems with four or more cabinets, make sure that wall brackets (RWBF1) are installed
on both sides of the top cabinet, in addition to cabinet three.
11. Check to make sure the cabinets are parallel to the wall. Secure the floor fixtures attached to
the bottom cabinet to the floor with the customer-provided floor anchors.
12. Connect the data cable of each Expansion Cabinet to the applicable data cable connector on
the Base Cabinet
should be connected to the connector labeled "CAB. 2", the cable from the second Expansion
Cabinet to the "CAB. 3" connector, etc.)
13. Install ground wiring, AC and reserve power cabling, and PCB cabling per the
"Recommended Installation Sequence" on Page
14. Fill out cabinet/slot identification labels on each cabinet and reinstall covers on the cabinets.
(The top cover should be installed on the top cabinet.)
5-22
(Figures 5-10
and 5-28). (The data cable from the first Expansion Cabinet
5-7.
Strata DK I&M
6/00

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Strata dk 424iDk 14Dk 424Dk40iDk 424i

Table of Contents