Close-Out Procedure - BIG ASS FANS Powerfoil 8 Installation Manual

Hide thumbs Also See for Powerfoil 8:
Table of Contents

Advertisement

Date:
Company:
Address:
City/State/ZIP:
Contact Name:
E-mail:
The installation is complete and on time in accordance with the original Check-In document. If not, explain:
Conduit runs are installed in accordance with the Check-In document, Scope of Work, and Layout. If not, explain:
The fans are correctly placed in accordance with both the Check-In document, Scope of Work, and Layout. If not, explain:
Breaker size and wire type are in accordance with the Check-In document, Scope of Work, and Layout. If not, explain:
All safety rules and regulations met in accordance with the Check-In document, Scope of Work, and Layout. If not, explain:
Fans have been running for over an hour and operate without visible defect or issue.
Angle irons are securely fastened and are without any apparent problems in accordance with installation techniques discussed
at check-in.
If extension tube is 4 ft (1.2 m) or longer, guy wires are in place and there is no evidence of a wobble.
Supervisor or contractor has supplied and explained the Installation Guide. If not, explain:
The supervisor or contractor has explained and I understand how to operate fan including starting/stopping, speed operation,
and power disconnect. If not, explain:
Time in/out and duration are in accordance with Check-In document.
Additional comments:

Close-Out Procedure

(for Big Ass
Job Name:
Purchase Order No.:
Phone:
2348 Innovation Drive
Lexington, KY 40511
Phone: 1-877-BIG-FANS
Fax: (859) 967-1695
www.bigassfans.com