Ship-Ahead Input/Output Cabinet
®
Installation Manual – 250-400kVA, 60Hz
AC Power
For Business-Critical Continuity™

Advertisement

Table of Contents
loading

Summary of Contents for Liebert Ship-Ahead Input/Output Cabinet NXL

  • Page 1 Liebert Ship-Ahead Input/Output Cabinet ® ™ Installation Manual – 250-400kVA, 60Hz AC Power For Business-Critical Continuity™...
  • Page 2: Product Warranty Registration

    For repair or maintenance service outside the 48 contiguous United States, contact Liebert Services, if available in your area. For areas not covered by Emerson Network Power Liebert Services, the authorized distributor is responsible for providing qualified, factory-authorized service.
  • Page 3: Table Of Contents

    Input/output conduit detail drawing, 250-300kVA Liebert NXL UPS ..... . 9 Figure 2 Input/output conduit detail drawing, 400kVA Liebert NXL UPS ......10 Figure 3 Top cable entry routing and installation order .
  • Page 5: Save These Instructions

    MPORTANT AFETY NSTRUCTIONS SAVE THESE INSTRUCTIONS This manual contains important instructions that should be followed during installation of your Lie- ™ bert NXL Input/Output Cabinet. Read this manual thoroughly, paying special attention to the sec- tions that apply to your installation, before working with the UPS. Retain this manual for use by installing personnel.
  • Page 6: Mechanical Installation

    NOTICE Three-phase input supply required. The standard Liebert NXL UPS is suitable for connection to three-phase, four-wire (+ Earth) TN-C, TN-S, IT-G, IT-IG or, three-phase, three-wire plus ground, IT-UG. If using with IT Power system, a 4-pole disconnect device must be included as part of building installation.
  • Page 7 1.4.1 Moving the Cabinets The Liebert NXL Input/Output Cabinet can be handled with a forklift or similar equipment. When moving the unit by forklift, care must be taken to protect the panels. Do not exceed a 15-degree tilt with the forklift. Bottom structure will support the unit only if the forks are completely beneath the unit.
  • Page 8: Electrical Installation

    LECTRICAL NSTALLATION This chapter provides guidelines for qualified installers who must have knowledge of local wiring practices pertaining to the equipment to be installed. WARNING Risk of electrical shock. Can cause injury or death. Check for voltage with both AC and DC voltmeters before working within the cabinet. Only properly trained and qualified personnel wearing appropriate safety headgear, gloves, shoes and glasses should be involved in installing the cabinet or preparing the cabinet for installation.
  • Page 9 All operations described in this section must be performed by properly trained and qualified electricians or technical personnel. If any difficulties are encountered, contact Liebert Services. See the back page of this manual for contact information.
  • Page 10: Table 1 Current Ratings-Rectifier Input

    Top Cable Entry When making the power connections, the recommended order of pulling and installing cables is to start from the top connections to the bottom connections. The cables must be routed around the fault braces (see Detail in Figure 3). This is to prevent the cables from contacting other busbars.
  • Page 11: Current Ratings-Battery

    Table 4 Current ratings—battery UPS Rating Nominal VDC Notes on Tables 1. Nominal input current (considered continuous) is based on full-rated output load. Maximum current includes nominal input current and maximum battery recharge current (considered noncontinuous). Continuous and noncontinuous current are defined in NEC 100. Maximum input current is controlled by the current limit setting which is adjustable.
  • Page 12: Recommended Lug Sizes

    Table 6 Recommended lug sizes T&B Series 54000 Cable Size One Hole #8 AWG 54930BE #6 AWG 54905BE #4 AWG 54906BE #2-3 AWG 54942BE #1 AWG 54947BE #1/0 AWG 54950BE #2/0 AWG 54951BE #3/0 AWG 54965BE #4/0 AWG 54970BE 250kcmil 54913BE 300kcmil 54914BE...
  • Page 13: I Nstallation D Rawings

    NSTALLATION RAWINGS Figure 1 Input/output conduit detail drawing, 250-300kVA Liebert NXL UPS LOW VOLTAGE 1.5" CONDUI T TOP VIEW DC POSITIVE DC NEGATIVE SEE NOTE 6 FRONT ( 14 ) ( 22 ) 1.75 ( 44 ) ( 22 )
  • Page 14: Figure 2 Input/Output Conduit Detail Drawing, 400Kva Liebert Nxl Ups

    Figure 2 Input/output conduit detail drawing, 400kVA Liebert NXL UPS LOW VOLTAGE 1.5" CONDUI T TOP VIEW DC POSITIVE DC NEGATIVE SEE NOTE 6 FRONT O .56 (14 ) ( 22 ) .98 ( 25 ) 1.75 (44 ) (22) 1.10...
  • Page 15: Figure 3 Top Cable Entry Routing And Installation Order

    Figure 3 Top cable entry routing and installation order DC (POSITIVE) DC (NEGATIVE) GROUND (TOP ENTRY) BYPASS NEUTRAL FAULT BRACE BYPASS INPUT BYPASS INPUT FAULT BRACE RECTIFIER INPU T RECTIFIER INPU T FAULT BRACE OUTPUT OUTPUT GROUND (BOTTOM ENTRY) OUTPUT NEUTRAL FRONT VIEW OUTPUT CONDUIT FAULT BRACE...
  • Page 16: Figure 4 Bottom Cable Entry Routing And Installation Order

    Figure 4 Bottom cable entry routing and installation order DC (POSITIVE) DC (NEGATIVE) GROUND (TOP ENTRY) BYPASS NEUTRAL FAULT BRACE BYPASS INPUT BYPASS INPUT FAULT BRACE RECTIFIER INPU T RECTIFIER INPUT FAULT BRACE OUTPUT OUTPUT GROUND (BOT TOM ENTRY) OUTPUT NEUTRAL FRONT VIEW FAULT BRACE BYPASS INPUT...
  • Page 17: Figure 5 Floor Mount Brackets-Standard And Optional Layout

    (The final installation will always require the unit to be bolted to another Liebert NXL product.) Failure to comply with these instructions could result in equipment damage and/or injury to personnel.
  • Page 18 Installation Drawings...
  • Page 20 While every precaution has been taken to ensure the accuracy and completeness of this literature, Liebert Corporation assumes no responsibility and disclaims all liability for damages resulting from use of this information or for any errors or omissions.