Air-to-water Heat Pump
19.2 Electric wiring work
19.2.1 Wiring principle
(1) General principles
Wires, equipment and connectors supplied for use on the site must be in compliance with
◆
provisions of regulations and engineering requirements.
Only electricians holding qualification are allowed to perform wire connection on the site.
◆
Before connection work is started, the power supply must be shut off.
◆
Installer shall be responsible for any damage due to incorrect connection of the external circuit
◆
of the unit.
Caution --- Must use copper wires.
◆
(2) Connection of power cable to the electric cabinet of the unit
Power cables should be laid out through cabling trough, conduit tube or cable channel.
◆
Power cables to be connected into the electric cabinet must be protected with rubber or plastic
◆
to prevent scratch by edge of metal plate.
Power cables close to the electric cabinet of the unit must be fixed reliably to make the power
◆
terminal in the cabinet free from an external force.
Power cable must be grounded reliably.
◆