Never attempt to fill a hot empty boiler.
Make sure that the area around the boiler is clear and free from combustible materials,
gasoline, and other flammable vapors and liquids.
Safe reliable operation of this boiler requires that the burner be checked and adjusted by a
qualified oil serviceman using combustion test instruments.
Failure to perform all of the checks outlined in the following procedure could result in
unreliable operation, damage to the boiler not covered under warranty, property damage,
or unsafe operation.
All boilers equipped with burner swing door have a potential hazard which can cause
severe property damage, personal injury or loss of life if ignored. Before opening swing
door, turn off service switch to boiler to prevent accidental firing of burner outside the
combustion chamber. Be sure to tighten swing door fastener completely when service
is completed. In addition, the burner power cord will have to be disconnected from the
receptacle in the front jacket.
Use the following procedure for initial start-up of the boiler:
1) Ensure that the boiler is filled to the normal water level.
2) Verify that the vent system is properly installed and free of obstructions prior to start-up of the boiler. Refer to Section VII
for more information.
3) Inspect all wiring for loose or uninsulated connections, proper size fuses installed, etc.
4) Verify that oil tank is filled with #2 fuel oil meeting ASTM D396 specifications, oil piping has been tested and is air tight,
and shutoff valve(s) are closed.
5) Check initial settings of oil burner air band and air shutter, head setting etc., and readjust if needed. See Table 12.1 for
setup and combustion data pertaining to a particular boiler/ burner combination.
6) Ensure the burner is tightly secured to the burner swing door creating an airtight seal.
7) Attach plastic hose to oil pump vent fitting and provide a container to catch oil during oil pump bleeding procedure.
8) Install 0-200 PSI pressure gauge into oil pump gauge port.
9) Open all oil line shutoff valves.
10) Open flame observation port cover on burner swing door to see flame.
11) Adjust system thermostat to highest setting.
12) Set pressure limit control to suit individual requirements of the installation. For most systems, the cut-in pressure should
be set at 0.5 psi with a 1 psi differential.
13) Turn the line service switch to "ON" position.
14) Crack open vent fitting on the oil pump and allow burner to run until a solid oil stream, free of air bubbles, flows for 15
seconds into container. As the vent fitting is closed, the burner should fire and flame should be visible through observation
port immediately (or after prepurge timing has expired, if a burner is so equipped). Refer to burner instructions for more
details.
15) Immediately upon firing the boiler, check the smoke level. If the smoke level is in excess of a #1, open the air adjustment
to bring the smoke level below a #1.
16) Make sure that the oil pressure matches that shown in Table 12.1 for the burner supplied. Adjust pressure if required.