1. PREPARATION OF THE SITE

The machine is delivered in a cardboard box screwed onto a wooden pallet.
A. Unpack the machine
-
Cut the tightening strap with shears.
-
Open the cardboard box and take the accessories' container out.
-
Make screws loose by slightly inclining the cardboard box.
-
Take the machine out of the cardboard box and put it on wooden blocks.
-
Remove screws and washers used for transport.
B. Install the machine and preparation of the site
-
Put the machine in its final place and level it up with the help of rubber washers, as necessary.
-
The machine must be placed on a horizontal surface.
-
There must be a free space of 5 cm behind the machine and the ventilation holes on the top of the machine
must not be obstructed.
-
A socket with a ground system and a water-supply pipe corresponding to the characteristics of the machine
are sufficient for connecting.
Set up cup racks after making adjustments.

2. HYDRAULIC CONNECTION

A water softener is necessary.
Water Intake
-
Pressure ranging from 0 to 10 bar
-
Connection : 3/8 gas female socket (male plug on machine)
-
Pipe with a minimum 8 mm internal diameter
-
Stop valve to be set up.
Drainage
-
Connection : 3/4 gas female socket (male plug on machine)
-
Pipe with a minimum 12 mm internal diameter.

3. ELECTRIC CONNECTION

-
.None of the switches must be in ON position.
-
Make sure that the voltage, frequency and power values marked on the descriptive plate of the machine are
in conformity with the electric network mains.
-
Mount a plug on the end of the machine cable (plug with grounding: green/yellow wire).