Condensate Connection - Worcester 29CDi GC 47-406-34 Installation, Commissioning And Servicing Instructions

Wall hung rsf gas fired condensing combination boiler
Table of Contents

Advertisement

1
3
Fig. 33 Plume distance to opening
1
Opening in building
2
Flue discharge
3
Plume deflector
4
Minimum 1500mm from an opening in the building
6 720 803 599 (2012/06)
4
2
6720643895-119.1Wo
4.7

CONDENSATE CONNECTION

Never terminate or discharge into any open source, including; sink,
bath, shower, bidet, toilet etc.
Any external condensate pipe work of excessive runs
should be protected with weather resistant insulation to
help prevent freezing.
B Ensure that the condensate drain is 22mm diameter plastic pipe. It
must fall at least 52mm per metre towards the outlet
B A 22mm adaptor pipe is contained in the fitting pack.
Fig. 34 Fitting siphon
INSTALLATION
27