4.2 Unit handling

Use 4 supporting points to move the units (refer to diagram).
Avoid unstable move to prevent unit drop off.
Do use special rope to tie the units for transportation.
Do not touch the fin to avoid injury.
Keep the plastic bag from reach of children.

4.3 Unit installation

Ensure the base is solid to support the unit.
Consider the location for drainage and piping installation.
Screw bolt to secure the 4 corners of the unit.
Use rubber absorber to prevent transfer of vibration.

4.4 Installation of Master and Slave unit

Both master and slave unit must be positioned side by side and installed in the same level.
The distance between master and slave unit shall be more than 10mm.
Copper part accessories are packed with the outdoor units.
All piping should be insulated.
Gas and liquid piping should be connected paralleled to each other.
Balance piping must be installed. It should be connected through the hole of side panel, base panel or the
piping connection position with the other outdoor unit.
Balance piping shall be installed horizontally and it must be lower than the access valve of balance piping.
Balance piping shall not be touching any other parts.