Burner Tray Removal; Gas Valve Removal; Gas Valve Adjustment - Robertshaw (Invensys) 7000 Series 2-Stage Gas Valve With Solenoid Valve - Raypak 133 Installation & Operating Instructions Manual

Hot water supply heaters
Table of Contents

Advertisement

burner Tray Removal

1. Shut-off power and gas supply to the heater.
Disconnect union(s) and pilot tubing, then loosen
and remove burner hold-down screws.
2. Disconnect wires at gas valve and slide burner
drawer out.

Gas Valve Removal

1. Shut-off gas supply to the heater. Remove gas pip-
ing to gas valve inlet.
2. Disconnect wires, pilot tubing and bleed line, if
required.
3. Turn vertical gas pipe from manifold slightly and
unscrew gas valve.
4. Reverse above procedure to re-install.
Gas Valve Adjustment - Robertshaw
(Invensys) 7000 Series 2-Stage Gas
Valve with Solenoid Valve
NOTE: Attach a manometer and check the manifold
pressures –both high fire and low fire– before
making any adjustments.
1. Turn the heater off.
2. Remove the 3/8" nut or the #10 Torx screw.
3. Lift solenoid valve up, keeping the wires connect-
ed to the solenoid valve.
4. If only low fire adjustment is needed, go to Step 9.
5. Using a 3/8" wrench, carefully remove the alu-
minum cap that was under the solenoid
valve-count # of turns when removing the cap.
Be careful not to drop the cylinder (weight) or the
small spring that is under the cap –see Fig. 39.
COMBINATION FLAME SENSOR/
IGNITER AND PILOT BURNER
Fig. 38: Typical Burner Tray Illustrated
6. Remove the spring and store in a safe place.
7. Using an Allen wrench, turn the screw clockwise to
8. Install the spring, weight and aluminum cap –tight-
9. For low fire adjustment, tighten the aluminum cap
10. Install 2-stage solenoid valve and turn heater on,
11. Repeat steps 3 to 10 until correct manifold pres-
12. Secure 2-stage solenoid valve by tightening the
46
increase or counterclockwise to decrease high fire
manifold pressure –see Fig. 39.
en the cap using same # of turns as was used in
removing the cap.
to increase and loosen to decrease low fire mani-
fold pressure.
check manifold pressures.
sures are obtained.
3/8" nut or #10 Torx screw.
Fig. 39: 2-Stage Gas Valve Adjustment (Invensys)

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents