This switch supports 1000BASE-LX5, 1000BASE-LX15, 1000BASE-LHX,
1000BASE-ZX, and 100BASE-FX SFP-compatible transceivers. To install an SFP
transceiver, do the following:
Consider network and cabling requirements to select an appropriate SFP
1.
transceiver type.
Insert the transceiver with the optical connector facing outward and the slot
2.
connector facing down. Note that SFP transceivers are keyed so they can
only be installed in one orientation.
Slide the SFP transceiver into the slot until it clicks into place.
3.
SFP transceivers are hot-swappable. The switch does not need to
N
:
OTE
be powered off before installing or removing a transceiver. However,
always first disconnect the network cable before removing a
transceiver.
SFP transceivers are not provided in the switch package.
N
:
OTE
G
ROUNDING THE
Before powering on the switch, ground the switch to earth as described below:
Ensure the rack on which the switch is to be mounted is properly grounded
1.
and in compliance with ETSI ETS 300 253
Ensure that there is a good electrical connection to the grounding point on
2.
the rack (no paint or isolating surface treatment.)
Disconnect all power cables to the switch.
3.
Then attach the grounding wire to the grounding point on the rack.
4.
C
AUTION
connections have been disconnected.
C
HASIS
The earth connection must not be removed unless all supply
:
C