Use Mounting Cable Tie to fix cables.
Tower model
External Battery
External Charger
T1
10KRT model
6. Please refer to the specs of input current, output current and recommended
conductors listed as below :
a. AC input and output (75°C minimum copper wire)
Model
Maximum Current
4.5KVA
25A
6KVA
33A
8KVA
43.4A
10KVA
54.3A
b. Battery input
Model
Maximum Current
4.5KVA
19A
6KVA
25A
8KVA
33A
10KVA
41A
6KRT model
6000C model
Conductor Section
Torque force
AWG #10
AWG #9
AWG #8
23 lb-in
AWG #6
23 lb-in
Conductor Section
AWG #10
AWG #10
AWG #10
AWG #10
18

3.5. Operation Test and Installation Instruction

3.5.1. Start Up in Normal Mode
3.5.1.1. Open the terminal block cover on the rear panel (refer to 2.3.2)
Before start the installation, please make sure the grounding is
connected properly.
3.5.1.2. Make sure Utility breaker, UPS' Utility breaker and Bypass
breaker are On "Off" position.
3.5.1.3. Make sure the voltage of Utility matches with the input voltage
window of the UPS.
3.5.1.4. Connect the Utility separately to the terminal blocks of UPS' Utility
and Bypass Inputs. Switch on the Power Breaker of the
distribution panel and the breakers of the UPS' Utility and Bypass
Inputs, and then the UPS starts up. Green LEDs
up to show the Utility and Bypass Inputs are normal and the LCD
display with parallel function will illustrate from drawing A1,
drawing A2 to drawing B. Otherwise the LCD display will illustrate
from drawing A2 to drawing B.