Filter Setup
Assembly: See Figures 2 through 5 for filter assembly.

Loading Sand Media

1. To keep sand out of collector assembly, place plastic
sand shield over top of collector tube before pouring
sand into filter (See Figure 5).
2. To support laterals and prevent lateral breakage dur-
ing loading, fill tank about half full of water before
loading sand.
3. Pour sand into filter tank. See "Recommended Sand
Grades", Page 4, for correct type and quantity of
sand to use.
NOTICE: Make sure gasket area on top of tank is
free of sand before installing valve and clamp.
4. Before installing valve, double-check that correct
quantity of sand has been loaded (see Page 4).
5. Remove plastic sand loading shield and keep for fu-
ture use.
Valve Installation:
See Figures 6, 7, and 8
1. Install O-Ring on valve flange; make sure O-Ring is
clean, dry, and has no nicks, tears, or scrapes.
2. Make sure tank and valve flanges are clean and free
of sand; put valve on top of tank. Vertical pipe of col-
lector assembly inserts into base of valve.
3. Install clamp; make sure knob is positioned for easy
A. Insert first lateral into socket;
twist clockwise 1/4 turn
to lock lateral into hub.
Lateral is correctly installed
when slots face down.
Figure 2
C. Hold assembly up
near top of tank and
add remaining
laterals.
732 0294
Figure 3
B. Insert assembly
into top of
filter tank.
731 0294
Figure 5
access for filter maintenance. Valve port labeled
"PUMP" should point toward pump.
4. Tighten clamp knob until clamp ends (under bolt) are
1/4" (6mm) apart. Tap around outside of clamp with
a mallet to help seat clamp.
Hazardous pressure. Clamp will not
hold unless it is seated properly! DO NOT START
PUMP until clamp ends are 1/4" (6mm) apart or
less.
5. If clamp will not pull up to 1/4" (6mm) gap, wait
15-30 minutes and retighten. Tap clamp gently with
mallet to help seat clamp.
6. Connect pipe from pump discharge to valve port la-
beled "PUMP"; use union half provided. Assemble
union as follows for leakfree operation:
A. O-Ring and sealing surfaces must be clean.
B. Assemble hand tight only (no wrenches).
C. NO pipe compound or teflon tape on unions.
7. Complete all plumbing connections (see Page 5 for
piping requirements).
A. Pipe from valve RETURN port to pool return.
B. Pipe from valve WASTE port to waste.
C. Suction piping from pool to trap inlet on pump.
8. System is ready for startup.
NOTICE: If there are leaks from beneath valve/clamp
area, STOP PUMP, release all pressure, remove
clamp and valve and clean sealing surfaces.
D. After all
laterals are
securely in
sockets,
position
assembly on
centering
boss in
bottom of
tank.
Figure 4
::::
::::
::::
::::
::::
::::
Fill tank
::::
::::
::::
::::
::::
::::
::::
::::
::::
::::
::::
::::
::::
::::
about
::::
half full
of water
before
::::
::::
::::
::::
::::
::::
adding
sand.
6
733 0294
Sand Shield
keeps collector
hub assembly
clean when
loading filter.
734 0294

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Waterford systems high rate sand filter system

Table of Contents