Outline of procedure
For a trial operation, follow the procedure below:

Check before trial operation

.
Implementation of trial operation check
(In case of abnormal operation in trial operation)
* Ensure you write the check results of trial operation in the check lists 1 and 2. It will be an important document for
servicing or maintenance in the future.
Check before trial operation
Prior to the trial operation, confirm whether there is a fault with the installation work using "Check list 1".
Is the capacity of field fuse adequate?
Is the diameter of power source cable correct?
Is the control transmission line correct?
Is the power of indoor units collectively supplied?
Is the earth grounded?
Is the insulation good?
Is the voltage good?
Is the connecting cable diameter correct?
Is the branching kit correct?
Is the drain water flow sufficient?
Is the heat insulation of cables good?
Is there no short-circuit of discharge air of indoor/outdoor units?
Are vacuuming and addition of refrigerant performed after airtight test of refrigerant piping?
Are the valves fully opened?
Check additional amount of refrigerant
Calculate the additional amount of refrigerant from the pipe dia. at liquid side and length of pipe to be connected. Write
the total length of the liquid side pipes for each dia. in the following table, and calculate the additional amount of
refrigerant. (The refrigerant amount charged in the outdoor unit is only for the outdoor unit, and refrigerant for piping is
not included.)
Pipe diameter at liquid side (mm)
∅6.4
∅9.5
18
∅12.7
∅15.9
∅19.0
∅22.2

Procedure and summary of trial operation

Clear the error
End
(Indoor/outdoor connecting terminal: PQ, Type: Shield wire)
(10 MΩ or more )
(Within 380/400/415 ± 10%)
Standard refrigerant amount (kg/m) Total length of liquid side pipes (m) Additional refrigerant amount for each liquid pipe
0.030
0.065
0.115
0.190
0.290
0.420
Trial operation
[
Check the basic items, especially installation work. Ensure you write the
check lists 1 and 2
[
Implement check in sequence according to each flowchart of trial operation
procedure.
[
Refer to Troubleshooting to clear the error, and then implement the trial
operation again.
CHECK LIST 1
Outdoor unit
Outdoor unit
(Indoor unit)
(Connecting cables, branching kits)
Gas side
Liquid side
CHECK LIST 2
X
X
X
X
X
X
Additional refrigerant amount
132
A
Indoor unit
mm
2
Indoor unit
Cable diameter
MΩ or more
V for outdoor unit
Balance side
=
=
=
=
=
=
]
]
]
A
mm
2
mm
2
kg
kg
kg
kg
kg
kg
kg