The following tasks must be performed by a qualified
service technician.
Logs
Frequency: Annually
By: Qualified Service Technician
Tools needed:
Protective gloves.
Inspect for damaged or missing logs. Replace as
necessary. Refer to Section 14.D. for log placement
instructions.
Verify correct log placement and no flame impingement
causing sooting. Correct as necessary.
Firebox
Frequency: Annually
By: Qualified Service Technician
Tools needed:
Protective gloves, sandpaper, steel wool,
cloths, mineral spirits, primer and touch-up paint.
Inspect for paint condition, warped surfaces, corrosion
or perforation. Sand and repaint as necessary.
Replace fireplace if firebox has been perforated.
Control Compartment and Firebox Top
Frequency: Annually
By: Qualified Service Technician
Tools needed:
Protective gloves, vacuum cleaner, dust cloths
Vacuum and wipe out dust, cobwebs, debris or pet hair.
Use caution when cleaning these areas. Screw tips that
have penetrated the sheet metal are sharp and should
be avoided.
Remove all foreign objects.
Verify unobstructed air circulation.
12
Heatilator • RBV4236/RBV4842 • 4048-210 • Rev S • 6/10
Burner Ignition and Operation
Frequency: Annually
By: Qualified Service Technician
Tools needed:
Protective gloves, vacuum cleaner, whisk
broom, flashlight, voltmeter, indexed drill bit set, and a manom-
eter.
Verify burner is properly secured and aligned with
igniter.
Clean off burner top, inspect for plugged ports, corrosion
or deterioration. Replace burner if necessary.
Replace ember materials with new dime-size pieces.
DO NOT block ports or obstruct lighting paths. Refer to
Section 14 for proper ember placement.
Verify batteries have been removed from battery back-
up IPI systems to prevent premature battery failure or
leaking.
Check for smooth lighting and ignition carryover to all
ports. Verify that there is no ignition delay.
Inspect for lifting or other flame problems.
Verify air shutter setting is correct. See Section 14.J.
for required air shutter setting. Verify air shutter is clear
of dust and debris.
Inspect orifice for soot, dirt and corrosion. Verify orifice
size is correct. See Service Parts List for proper orifice
sizing.
Verify manifold and inlet pressures. Adjust regulator as
required.
Inspect pilot flame pattern and strength. See Figure 3.1
for proper pilot flame pattern. Clean or replace orifice
spud as necessary.
Inspect IPI flame sensing rod for soot, corrosion and
deterioration. Clean with emery cloth or replace as
required.
Verify that there is not a short in flame sensing circuit
by checking continuity between pilot hood and flame
sensing rod. Replace pilot as necessary.
Figure 3.1 IPI Pilot Flame Patterns