Commissioning

4.1

Tools to commission the converter

Operator panels for commissioning, diagnostics and controlling inverters
PC tools for commissioning, diagnostics and controlling the converter
Converters with CU250S-2 Control Units
Getting Started, 10/2013, FW V4.6, A5E32899990B AA
BOP-2 (Basic Operator Panel) - for snapping onto the inverter
Two-line display
Guided basic commissioning
Backing up and transferring the inverter settings
IOP (Intelligent Operator Panel) - for snapping onto the inverter
Plain text display
Menu-based operation and application wizards
Backing up and transferring the inverter settings
Door mounting kit for IOP/BOP-2
For installation of the BOP-2 or IOP in a control cabinet
door.
Degree of protection with IOP: IP54 or UL Type 12
Degree of protection with BOP-2: IP55
For mobile use of the IOP:
IOP handheld with IOP housing, power supply unit and
rechargeable batteries as well as RS232 connecting cable
If you are using your own connecting cable, carefully note the
maximum permissible length of 5 m.
PC Connection Kit
Includes a STARTER DVD and USB port.
STARTER Commissioning tool (PC software)
Connection to the inverter via USB port, PROFIBUS or
PROFINET
Downloading: STARTER
(http://support.automation.siemens.com/WW/view/en/1080498
5/133200)
Drive ES Basic
As an option to STEP 7 with routing function via network limits
for PROFIBUS and PROFINET
4
Order number
6SL3255-0AA00-4CA1
6SL3255-0AA00-4JA0
6SL3256-0AP00-0JA0
6SL3255-0AA00-4HA0
6SL3255-0AA00-2CA0
STARTER on DVD:
6SL3072-0AA00-0AG0