INSTALLATION
RIGGING AND LIFTING
The engine/generator is fitted with lifting eyes. Attach
wire rope or chain slings capable of supporting the
engine/generators weight to the eyes and lift the engine/gen-
erator by means of tackle attached to these slings. The lifting
eyes have been designed to carry the full weight: auxiliary
slings are not necessary.
NOTE:
Rigging work is best done by someone experienced
and competent in handling machinery.
LOCATION AND MOUNTING
A solid, level mounting platform is very important for the
proper operation of your generator. Select a location that will
allow adequate space on all sides for ventilation and servic-
ing. Locate the generator away from living quarters, and
away from bilge splash and vapors.
Refer to WESTERBEKE'S installation manual for detailed
information on installing a Marine Generator in a boat.
3/4" PLYWOOD-BOLTED/FIBERGLASSED
IN PLACE
BATTERY ATTACHMENTS,
TO STARTER MOTOR
REFER TO THE WIRING
DIAGRAM IN THIS MANUAL
(-) NEGATIVE
LEAD
USE THE PAN AS A TEMPLATEFOR
LOCATING THE PROPER MOUNTING
HOLES TO THE PLYWOOD BASE
(+) POSITIVE
LEAD
SIDE VIEW
RAW WATER INLET O.Sin (2.7mm)
1.0.
HOSE
BOTTOM VIEW
TOP VIEW '
WATER OUTLET
AND
DlSCHr.RGE.
HOSES O.Sln (2.7mm) 1.0.
·FDUR
1/2"
BOLTS
DIMENSION (INCHES AND MM)
DIMENSIONAL DRAWINGS
For dimensional drawings. View the drawings on the
Westerbeke website www.westerbeke.com for the most
current drawings with dimensions.