Opacity monitor
Table of Contents

Advertisement

Yearly:
Clear stack or off stack zero
All quarterly checks
Remove transceiver and retro, clean air plenum
Replace any worn hoses and gaskets
Check all system operations
General
Corrective and preventive maintenance schedules should be adjusted according to site specific conditions to
ensure the maximum availability of accurate measurement data. Routine checks should be implemented to:
Observe and correct the operation of the air-purge system giving particular attention to keeping the optical path
within the mounting flanges clear of dirt build-up.
Observe and correct the operation of peripheral accessory equipment such as recorders, computers, etc.
Observe and correct the stack zero measurement whenever a clear stack condition exists. Care should be exercised
to ensure that both transmittance and opacity measurements are at their prescribed values.
Verify that instrument operating manuals are available and that maintenance logs are properly maintained and
reviewed.
Every 3-5 Years:
EMS recommends periodical, depending on the severity of the sensor locations 3-5 years between overhaul of our
opacity system to keep them working at their optimal level. Overhauls become necessary do to the fact that over
time dust, out gassing of electronic parts, removing protective covers, etc., manifest itself as overall optics
degradation causing more frequent adjustments and poor performance of the opacity monitor.
To schedule call EMS service department 203.935.0102 ext 14 or email;
service@emsct.com