Generator Operation/Shutdown - MULTIQUIP GA-6REA Operation And Parts Manual

Robin gasoline engine
Table of Contents

Advertisement

GA-6RE/GA-6REA — GENERATOR OPERATION/SHUTDOWN
5. Read the voltmeter on the front panel of the generators
(Figure 22) and verify that 240 VAC is present at the
240V twist-lock receptacle. Using an external voltmeter
verify that 120V is present at the 120V twist-lock and
GFCI duplex receptacles.
Figure 22. 60 Hz Output Receptacles
When the full power switch is in the 240
volt (down) position, you can take up to
NOTE
half of the rated power of the generating
set at 120 volts from the GFCI duplex
receptacle and up to half of the rated power of the set at 120
volts from the 120V twist-lock receptacle; or full rated power
of the genset at 240 volts from the 240V twist-lock
receptacle.
When using a combination of dual
receptacles, total load should not exceed
NOTE
the rated capacity of the generator.
Connecting the Load
1. If small wattage power tools are required, connect them
to the 60 Hz output receptacles at this time.
GA-6RE/GA-6REA A.C. GENERATORS — OPERATION & PARTS MANUAL — REV. #0 (06/06/05) — PAGE 27
Stopping the Engine
1. Place the main circuit breaker (Figure 23) in the OFF
position.
Figure 23. Main Circuit Breakers (Off)
2. Place the idle control switch (Figure 24) in the OFF
position.
Figure 24. Idle Control Switch (Off)
3. Let the engine run at idle with no load for 2-3 minutes.
4. To shut-down the engine, place the generator's
operation switch (Figure 25) in the OFF position.
Figure 25. Generator On/Off Switch (Off)
5. Place the engine fuel valve lever (Figure 26) to the "OFF"
position. "
Figure 26. Engine Fuel Valve Lever (OFF Position)
6. Remove the all loads from the generator.

Advertisement