6. If the engine has started, slowly return the choke lever
(Figure 12 ) to the "OPEN" position. If the engine has not
started repeat steps 1 through 5.
7. Before the generator is placed into operation, run the engine
for 3-5 minutes. Check for abnormal smells, fuel leaks, and
noises that would associate with lose components.
8. Refer to the AC voltmeter (Figure 15) on the control
box. The voltage indicated on the voltmeter should be
120 VAC with no load applied.
Figure 15. AC Voltmeter (120 VAC)
11. If desired, verify with a voltmeter (Figure16) that 120
VAC is present at the GFCI duplex receptacle and the
120V twist-lock receptacle.
Figure 16. 120 VAC GFCI Receptacle
Connecting the Load
1. Connect the load to the output receptacles.
2. Place the main circuit breaker (Figure 17) in the ON
position.
Figure 17. Main Circuit Breaker (ON)
PAGE 24 — MQ GA-2.9R A.C. GENERATOR— OPERATION & PARTS MANUAL — REV. #0 (10/28/04)
MQ GA-2.9R— INITIAL START-UP ENGINE/OPERATION
Stopping The Engine
Normal Shutdown
1. Place the main circuit breaker (Figure 10) in the OFF
position.
2. Remove the load from the generator, and let the engine
run at idle for 3-5 minutes with the idle control switch in
the ON position (Up)
5. Place the engine ON/OFF switch (Figure 18) in the " OFF "
position.
Figure 18. Engine ON/OFF Switch (OFF)
6. Place the engine fuel valve lever (Figure 19) to the "OFF"
position. "
Figure 19. Engine Fuel Valve Lever (OFF Position)
Emergency Showdown
1. Place the
engine ON/OFF swith (Figure 18) in the
"OFF" position.

Advertisement