Figure 34. A-frame assembly
Figure 35. A-frame mounting
Table 8. Spacing between A-frames
Structure
A-frame Nº
2 PV modules
3
Figure 36. Spacing between A frame profiles
7. SUPPORTING STRUCTURE ASSEMBLING MANUAL
7.1.
Installation sequence
The A-frame assembly should be clamped using the nuts & bolts supplied
with the kit.
The mounting to the floor should be carried out using appropriate fixings
for the substrate. If there are questions regarding to validity of the sup-
porting surface or questions relating top safety then a qualified structural
Engineer should be consulted.
The A-frame mounting should be performed, in a way that the spacing
between them is:
Spacing
Profile overhang
732 mm
270 mm
Flat roof
(Figure 34)
(Figure 35)
(Table 8, Figure 36).