Installing
Installing and initially configuring the switch
Installing a 2/8q FC Switch involves the following steps, each of which is discussed in the
following sections:
Unpack the switch and verify carton contents
The 2/8q FC Switch is shipped with the components shown in
Figure 5: Switch carton contents
28
Unpack the switch and verify carton
Mount the
switch, page 29
Install SFP
transceivers, page 34
Connect the
cables, page 35
Configure the
switch, page 36
1
3
4
1
2/8q FC Switch
2
2/8q FC Switch Quick Start Installation Instructions (printed)
3
Power cable (approved for use in the United States)
4
Mounting adapter brackets
5
Screws for the mounting adapter brackets (6)
6
Rubber feet (4)
7
Small Form Factor Pluggable (SFP) transceivers (4)
contents, page 28
2
7
6
5
HP StorageWorks 2/8q Fibre Channel Switch Installation Guide
Figure
5.