144. Install the supplied heater hose onto the heater tube
on the passenger side of the water crossover.
145. Verify that the coolant petcock is closed, then refill
the coolant system.
146. Fill the intercooler system with a 50/50 blend of
water and coolant poured into the recovery tank. Fill the
tank until the water level is roughly 1" from the top of the
threaded neck.
XIV. Installing Coil Covers (Does Not Apply To 1585)
147. Lift the recovery tank off the strut tower bolts and
fold it forward.
148. '05 & '06 applications should tape off the strut
tower brackets to prevent damaging the covers during
installation. On some '05 & '06 vehicles, it may be
necessary to clearance the flange on the bottom of the
strut tower brackets in order for the covers to fit properly.
©2011 Edelbrock LLC
Part #1580 & 1585
Edelbrock 4.6L Ford Supercharger System
for 2005 and later Mustang GTs
Installation Instructions
149. Install the coil cover brackets onto the coil covers
with the raised portion of the bracket facing towards the
top of the cover, while the lower 'L' portion faces in
towards the center of the cover, as shown below.
150 Apply a small amount of blue loctite to the thread of
each bolt supplied in hardware bag #8, then tighten them
into the threaded holes of the coil covers.
151. Remove the engine oil dipstick, then pull the main
wiring harnesses off the valve cover studs on both sides
of the engine bay.
152. Lube the grommet supplied with the driver side
cover with silicone spray, then slide it over the dipstick
tube and wiggle it into place with your thumbs as you
lower the driver side cover into place.
Page 27
Brochure #63-1580
Rev. 1/11 - AJ/mc

Advertisement

loading

This manual is also suitable for:

E-force 1585