100. Insert the water crossover into the gap between the
intercooler manifold and the and the supercharger drive
pulley. There are no bolts that directly attach the
crossover to the manifold, so it will need to be held steady
as the supercharger is installed.
101. With the help of an assistant or a cherry picker,
carefully lower the supercharger assembly onto the
cylinder heads. Be especially careful not to pinch any
wires between the supercharger and the cylinder heads.
Orient the attached 3/8" hose around the back of the
manifold in the direction of the brake booster as the
supercharger is lowered.
102. Push the supercharger as far to the rear of the
engine bay as space allows so that the bolts supplied in
hardware bag #6 can be inserted into the provisions on
the crossover. Pull the crossover forward against the
bolts, then torque them to 7-1/2 ft/lbs with a 10mm
socket.
103. Ensure correct alignment of the supercharger by
looking through the injector holes to verify that they are
aligned with the injector provisions of the cylinder head
and that the manifold is centered left to right as well as
front to back on the engine block.
©2011 Edelbrock LLC
Part #1580 & 1585
Edelbrock 4.6L Ford Supercharger System
for 2005 and later Mustang GTs
Installation Instructions
104. Use a 10 mm socket to install the intake bolts
supplied in hardware bag #1 then torque them to 8 ft/lbs
in the sequence shown below.
105. Install the new fuel injectors (not included in 1585)
into the stock fuel rails by applying a bit of o-ring lube to
both o-rings of each injector, sliding the stock retaining
clips onto the injectors, then pushing each injector into the
rail until the clips snap into place.
106. Align each of the fuel injectors with its prospective
well, then pull the top of the rail outboard so that the the
brackets will clear the runner flanges as you push the rail
down. Make sure that the TMAP wiring harness is routed
below the driver side rail. The rails and injectors are fully
seated once the rail brackets contact the runner bosses.
Use a 5mm allen tool to secure the rails with the M6
socket head bolts supplied in hardware bag #2.