Installation Guide Mars Pro-S1000 Series Applicable Model(s): Mars Pro-S1000, Mars Pro-S1200 Version: 1.1 Due to regular upgrades of systems and products, ZKTeco could not guarantee exact consistency between the actual product and the written information in this manual.
Revision History Description Revision Date Author Reviewer Yang Kaijin Original Document V1.0 09/28/2021 The control board, and wiring Huang Liye V1.1 02/17/2025 diagram have been changed.
Page 3
1 Overview Mars Pro-S1000 Master Slave Master Slave Mars Pro-S1200 Side Lid Direction Indicator Traffic Indicator Authentication Reserve Mounting Top Lid Door Leaf Air Switch Holes (for Face Devices) Access Controller Board Servo Motor Turnstile Controller Board Infrared Sensor Drive Controller Core Component...
Page 4
2 Dimensions Mars Pro-S1000 Front View Side View 120mm 1355mm 50mm 245mm 650mm Top View Bottom View Bottom Mounting Hole 1355mm 60mm 1282mm Mounting Holes Wire Holes 28x18mm 40mm 50mm...
Page 5
Mars Pro-S1200 Front View Side View 120mm 1355mm 245mm Top View Bottom View Bottom Mounting Hole 1355mm 1282mm 60mm Wire Holes Mounting Holes 50x40mm 28x18mm...
3 System Composition The Mars Pro-S1000 and Mars Pro-S1200 can be combined to form a single, dual or multi-lane system, allowing the user to select the appropriate door leaf size according to actual needs. Single-lane Dimensions of the door leaf (available): (630*295mm)(H*W)(Standard) (630*425mm)(H*W)(Optional) (1047*295mm)(H*W)(Optional)
Page 7
4 Wiring Single-lane wiring Slave ECU-panel connection wire Ethernet cable / Access control cable Power cable Master Dual-lane wiring Slave Slave Master Master Remarks: The multi-lane wiring method is similar.
5 Installation Requirements 1. It is recommended that the turnstile must be installed on a horizontal solid platform with a height of 50mm to 100mm. 2. It is recommended that the turnstile should not be used in the corrosive environment. 3.
Page 9
7 Installation Cabinet Step 1 Remove the Top lid and Side Lid 1. Remove the four screws hidden under the top lid, then remove the top lid. 2. Remove the side lid that hang on the device.
Step 2 Determine the Mounting Location 1. Please refer to the user's manual and complete the power-on self test operation before installation. 2. Then place the cabinet according to the mounting distances shown in the diagram below. Take care to measure the distance between the bottom inside walls of the cabinets on the entrance side and exit side of the channel and make sure that the measurements are consistent.
Page 11
Step 4 Drill Holes and Place Bolts 1. Using a concrete drill bit, drill the mounting holes 60mm in depth at the center of each marked location. 2. Then insert the bolts vertically into the mounting holes as shown at right. 3.
Page 12
Step 6 Fixed Cabinet 1. After laying the PVC pipe, place the cabinet alignment bolts back into the mounting position. 2. Then insert the four washers and nuts into the bolts one by one. 3. Tighten the nuts to hold the cabinet in place. Don't tighten it completely until after you're sure it won't move anymore.
Page 13
Step 7 Close the Side Lide and Top Lid Close the side lid and top lid, and secure with screws.
Page 14
Step 8 Marking the Warning Line 1. It is recommended that warning lines be marked on the ground and used to alert users. 2. A warning line can alert users to wait outside the line until the previous user completes the verif ication process and passes through the turnstile.
Need help?