6.2.3
Shutdown
1. When your operation has completed, switch the "Master" and
2. Flip the toggle switch for the "Fan/Control" selection to "Off."
3. The unit is now off.
Note: It is advised to
have all the switches in
the off position before
operation of the load
bank as well as after
use.
other load toggle switches to "Off." This will remove the load from
the unit.
Note: It is advised to
allow the unit to run
without a load for
about 30 seconds to
allow the system to
cool down.