Page 1
Step 3: Hang the EPM on the bracket by the steps below. Following minimum clearance is required. Version 1.1 Export Power Manager 300mm EPM3-5G-PLUS 300mm 300mm Step 4: Fix the two locking screw on both side of the bracket and connect the grounding wire to the grounding screw.
Page 2
Connect cables LCD Setting of EPM 3.1 Grid input cable -> Grid Port 3.3 CT cables -> CT1/CT2/CT3 Ports After EPM is powered on, LCD needs to do the following settings. Connect the grid input cables to the grid connector and then Connect the CT connectors to the EPM CT ports, and make sure Setting Path 1: Settings(For 4.1) to the Grid port of the EPM as described below.
Page 3
4.4.2 Set Meter CT 4.6 Select Export Work Mode 4.11 Set CT Check Set the CT(Current Transformer) ratio according to the actual CT Average Mode: Each phase of inverter will generate the power The default ”CT Check Choose” is ON, the EPM will give an alarm used at site.
Need help?
Do you have a question about the EPM3-5G-PLUS and is the answer not in the manual?
Questions and answers