TRF372017
is a high-performance, direct up-conversion device, integrating a high-linear, low-noise IQ
modulator and an integer-fractional PLL/VCO. The device is capable of converting complex modulated
signals from baseband or IF directly up to RF frequencies ranging from 300 MHz to 4.8 GHz. The
PLL/VCO, along with the internal 2/4/8 divider configuration as shown in the following table, is used to
obtain the desired frequency.
VCO Frequency
Part
Number
Fmin
TRF372017
2400
This document outlines the basic procedures for connecting the evaluation module (EVM) to test
equipment for basic testing.
1
Power Requirements
The TRF372017 requires a 3.3-Vdc Vcc power supply through test-point TP2 and 5-Vdc Vcc power supply
through test-point TP5.
Removing jumper JP6 enables the onboard regulator. With the onboard regulator enabled, the 5-V supply
is regulated to provide 3.3 V, and no direct 3.3-V connection through TP2 is required. High-performance
analog measurements must not be performed using the onboard regulator.
2
TRF372017 Operating Procedures for Modulator and Internal VCO Mode
1. Connect the USB to the computer and the mini-USB to the EVM board.
2. Power-supply connections:
(a) Set the 3.3-V supply current limit to 450 mA.
(b) Set the 5-V supply current limit to 200 mA.
(c) Connect the 3.3-V supply to TP2, 5-V supply to TP5, and common ground to TP4.
(d) Switch on the Vcc 3.3-V supply.
(e) Switch on the Vcc 5-V supply.
3. Input connections: Use a DAC or an arbitrary waveform generator to provide I/Q input signals at 1.7
Vdc to J3/J4 and J9/J10. By default, the EVM ac couples the I/Q signals to the device.
4. Output connections:
(a) To measure the PLL output: Connect a spectrum analyzer to the SMA connector marked LON (J1)
or LOP (J5) to monitor the VCO output single-ended. These output nodes can be used for two
purposes:
(i) Check the PLL functionality and measure the frequency range.
(ii) Use the TRF372017 in the PLL/VCO mode alone.
(b) To measure the modulator output: Connect a spectrum analyzer to the SMA connector marked
RF_OUT (J6) to monitor the up-converted signal in the regular operational mode (default mode of
operation).
5. Run the TRF372017 GUI software.
6. Click Reset USB to reset the USB connection.
7. Click on Write All Regs to load the GUI default settings to the device.
8. On start, the LOP and LON outputs and the RF_OUT output are disabled. Enable them as follows:
All trademarks are the property of their respective owners.
SLWU068A – October 2010 – Revised November 2010
Submit Documentation Feedback
Div by 2
Fmax
Fmin
Fmax
4800
1200
2400
Copyright © 2010, Texas Instruments Incorporated
SLWU068A – October 2010 – Revised November 2010
TRF372017EVM
Div by 4
Fmin
Fmax
600
1200
User's Guide
Div by 8
Fmin
Fmax
300
600
1
TRF372017EVM

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TRF372017EVM and is the answer not in the manual?

Questions and answers

Summary of Contents for Texas Instruments TRF372017EVM

  • Page 1 8. On start, the LOP and LON outputs and the RF_OUT output are disabled. Enable them as follows: All trademarks are the property of their respective owners. SLWU068A – October 2010 – Revised November 2010 TRF372017EVM Submit Documentation Feedback Copyright © 2010, Texas Instruments Incorporated...
  • Page 2 10. Toggle the EN_CAL control from Idle to Exec Cal to perform a calibration and lock the PLL/VCO at the default setting. TRF372017EVM SLWU068A – October 2010 – Revised November 2010 Submit Documentation Feedback Copyright © 2010, Texas Instruments Incorporated...
  • Page 3 Divider, and Tx Divider settings. (f) Frequency calculations. By default, changing any control in the Freq Targets area initiates a recalculation of register values. SLWU068A – October 2010 – Revised November 2010 TRF372017EVM Submit Documentation Feedback Copyright © 2010, Texas Instruments Incorporated...
  • Page 4 VCO_TESTMODE control. When VCO_TESTMODE is set to On, the register 0 display shows both the count bits and a calculated value indicating the corresponding approximate frequency. TRF372017EVM SLWU068A – October 2010 – Revised November 2010 Submit Documentation Feedback Copyright © 2010, Texas Instruments Incorporated...
  • Page 5: Revision History

    Page ......................... • Changed document title NOTE: Page numbers for previous revisions may differ from page numbers in the current version. SLWU068A – October 2010 – Revised November 2010 Revision History Submit Documentation Feedback Copyright © 2010, Texas Instruments Incorporated...
  • Page 6 1.8pF 1.8pF +3.3V +3.3V LO_OUT_P LO_OUT_P 47pF 47pF RSVD2 RSVD2 +5.0V +5.0V +3.3V +3.3V +5.0V +3.3V 1.8pF 1.8pF 1000pF 1000pF (SHUNT 2-3) (SHUNT 2-3) .1uF .1uF .1uF .1uF 100uF 100uF LO_OUT_P 1.8pF 1.8pF RF_CP_OUT TP20 TP20 +3.3V +3.3V LO_OUT_N LO_OUT_N 47pF 47pF +3.3V...
  • Page 7: Serial Interface

    SERIAL INTERFACE LED BLUE LED BLUE .1uF .1uF .01uF .01uF BOARD STANDOFFS VBUS TP10 TP10 GND1 GND2 GND3 DATA DATA RDBK RDBK SCREW PHIL 4-40 X 3/8" SCREW PHIL 4-40 X 3/8" GND4 47pF 47pF 47pF 47pF DATA USB_SUPER-MINI_AB USB_SUPER-MINI_AB USBDM USBDP SCREW PHIL 4-40 X 3/8"...
  • Page 8: Evaluation Board/Kit Important Notice

    Evaluation Board/Kit Important Notice Texas Instruments (TI) provides the enclosed product(s) under the following conditions: This evaluation board/kit is intended for use for ENGINEERING DEVELOPMENT, DEMONSTRATION, OR EVALUATION PURPOSES ONLY and is not considered by TI to be a finished end-product fit for general consumer use. Persons handling the product(s) must have electronics training and observe good engineering practice standards.
  • Page 9: Important Notice

    IMPORTANT NOTICE Texas Instruments Incorporated and its subsidiaries (TI) reserve the right to make corrections, modifications, enhancements, improvements, and other changes to its products and services at any time and to discontinue any product or service without notice. Customers should obtain the latest relevant information before placing orders and should verify that such information is current and complete.