This user's guide provides an overview of the TRF2436 evaluation module (EVM) to
get you started using the TRF2436EVM right away. It also provides a general
description of the features and functions to be considered when using this module.
1
Introduction
2
TRF2436EVM Operational Procedure
3
Physical Description
1
Top Layer 1
2
Ground Plane Layer 2
3
Power Plane Layer 3
4
Bottom Layer 4
1
TRF2436EVM PARTS LIST
1
Introduction
1.1
Purpose
The TRF2436 EVM provides a platform for evaluating the TRF2436 high-power, dual-band RF front-end
under various signals, reference, and supply conditions. Use this document with the EVM schematic
diagram supplied. Using the TRF2436EVM, you can rapidly evaluate the TRF2436 with a minimum of
manual setup.
1.2
System Requirements
Use the following equipment when evaluating the TRF2436EVM:
+3.3-V power supply, 800 mA.
Signal generator: Agilent ESG Series (with baseband I/Q modulation option for modulated testing) or
equivalent.
Spectrum analyzer: Agilent PSA Series (with phase noise option) or equivalent.
Vector signal analyzer: Agilent 89600 Series for 802.16x modulated EVM testing or equivalent.
1.3
Power Requirements
The demonstration board requires only one supply for proper operation. Connect +3.3 V at P1 and the
return to P2. Always terminate active PA outputs before enabling the power supply.
Voltage Limits
Exceeding the maximum input voltages can damage EVM components. Undervoltage can cause improper
operation of some or all of the EVM components.
SLWU038 – August 2006
Submit Documentation Feedback
Contents
..........................................................................................
...........................................................
................................................................................
List of Figures
..........................................................................................
..............................................................................
...............................................................................
......................................................................................
List of Tables
.......................................................................
User's Guide
SLWU038 – August 2006
TRF2436EVM
1
2
3
4
4
5
5
6
TRF2436EVM
1