17 - Start -up checklist for 38RM-N Units (use for job file)

Preliminary information
Job name:................................................................................................................................................................................................
Location:.................................................................................................................................................................................................
Installing contractor:.............................................................................................................................................................................
Distributor:.............................................................................................................................................................................................
Start-up preformed by:............................................................... Date: ...............................................................................................
Equipment
Model 38RM-N:................................................................................ S/N...............................................................................................
Compressors
Circuit A
1. Model No. ..................................................................................
Serial No. ...................................................................................
2. Model No....................................................................................
Serial No.....................................................................................
3. Model No....................................................................................
Serial No.....................................................................................
Air handling equipment
Manufacturer..........................................................................................................................................................................................
Model No........................................................................................
Additional air handling units and accessories....................................................................................................................................
.................................................................................................................................................................................................................
Preliminary equipment check
Is there any shipping damage?..................................................... If so, where?................................................................................
.................................................................................................................................................................................................................
Will this damage prevent unit start-up?..............................................................................................................................................
Unit is level in its installation
Power supply agrees with the unit name plate
Electrical circuit wiring has been sized and installed properly
Unit ground wire has been connected
Electrical circuit protection has been sized and installed properly
All terminals are tight
All cables and thermistors have been inspected for crossed wires
All plug assemblies are tight
Check air handling systems
All air handlers are operating
All fluid piping is connected properly
All air has been vented from the system
Unit start-up
Oil level is correct
Compressor crankcase heaters have been energised for 12 hours
Unit has been leak checked (including fittings)
Locate, repair, and report any refrigerant leaks
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
.................................................................................................................................................................................................................
Check voltage imbalance: AB................. AC.................. BC..................
Average voltage = .................................... (see installation instructions)
Maximum deviation = ............................. (see installation instructions)
Voltage imbalance = ................................ (see installation instructions)
Voltage imbalance is less than 2%
Circuit B
1. Model No................................................................................
Serial No.................................................................................
2. Model No................................................................................
Serial No.................................................................................
Serial No......................................................................................