DISASSEMBLY PROCEDURES 4. Using the adjustable spanner wrench (p/n 129198), re- move the retaining ring (14). Remove the purge cover (15). NOTE: Before performing any disassembly, refer to the exploded parts drawing, which references all mandatory replacement parts. These parts should be replaced with new, and must not be reused under any circumstances –...
Page 5
ABS Second Stage Technical Maintenance Manual 12. Stand the valve assembly vertical on the head of the NOTE: Because the crown is o-ring sealed, poppet (7), with the lever facing up, and depress the valve it will not freely exit the valve body after it body to expose the locknut (1).
2. Install the exhaust grid (10) by inserting the upper tabs NOTE: Aqua Lung no longer requires mandatory into the casing. Push both sides in, followed by pressing in replacement of the exhaust valves. As long as the lower tabs.
Page 7
ABS Second Stage Technical Maintenance Manual 6. Apply a medium blade screwdriver to the slotted head of 9. Press the new LP seat (8) into the cavity in the head of the the adjustable crown (21), and turn the crown clockwise to poppet (7), with the smooth side facing out.
Page 8
Do not proceed to reassemble the ABS second stage any further until first following the adjustment procedures OUTLET for the valve assembly outlined in the following section.
Leave 1-2mm of play in lever 2. The Aqua Lung inling tool (p/n 100190) can be configured for a slotted or hex type crown orifice. Pull back the shaft of the tool to retract the adjusting stem. Insert the threaded inlet fitting of the ABS valve assembly into the female threaded...
FINAL ASSEMBLY & TESTING 5. Fit the purge cover (15) into the box bottom (19) and thread on the cover ring (14) by hand or snug it up using PROCEDURES the spanner tool (129198). 1. Insert the valve body (4) and lever assembly inside the box bottom (19) with the lever (3) facing up.
Page 11
ABS Second Stage Technical Maintenance Manual Second Stage Air Flow Test Subjective Breathing Test 1. Depress the purge cover fully to ensure that an adequate 1. Connect the first stage regulator to a calibrated test bench volume of air needed to clear the second stage flows through and pressurize the system to 3000 (±100) psi.
Page 12
Table 1: Troubleshooting Guide SYMPTOM POSSIBLE CAUSE TREATMENT 1. High first stage MP 1. Refer to First Stage Troubleshooting (should be 135-140 psi). Guide 2. LP seat (8) is worn or damaged. 2. Replace the seat 3. Reset the crown and/or locknut to 3.
Page 13
ABS Second Stage Technical Maintenance Manual Table 2: List of Tools and Service Kits PART # DESCRIPTION APPLICATION In-line Adjustment Tool 100190 Final adjustment and tuning In-line Test Gauge 111605 MP testing Magnifier with Illumination Sealing surface inspection Seat Extraction/Installation Tool...
Page 14
20, 27 O-ring 820015 O-ring 104913 Clamp Table 4: Recommended Cleaners and Lubricants LUBRICANT/CLEANER APPLICATION SOURCE Aqua Lung, PN 820466, or Lubrication Technologies ® Christo-Lube MCG 111 All o-rings 310 Morton Street Jackson, OH 45640 (800) 477-8704 CAUTION: Silicone rubber requires no lubrication or preservative treatment.
When it comes to issues of nitrox safety and compatibility, the concerns lie primarily with the regulator’s first stage as it is subjected to high inlet pressures. High inlet pressures lead to adiabatic compression or heating of the gas. The Aqua Lung or Apeks regulator produc condensed hydrocarbons (compressor oils) from the inside passageways of the first stage.
Need help?
Do you have a question about the ABS SECOND STAGE and is the answer not in the manual?
Questions and answers