CONTROLLER KEY FUNCTIONS
Regardless of the version of controller received, the
installer must ensure the following:
1. The controller power cable is wired up to the
power point
2
2. The controller communication cable is correctly
wired up to the heat pump
a. RJ 45 cable for V1.1 controller
3. With reference to the controller manual
a. The time of day is correctly selected on the controller
b. The operational mode is set per customer
requirement (i.e., default is option 1)
4. The heat pump is purged by the controller during the
commissioning of the heat pump unit
a. Press and hold the "menu" or "OK" button on the
controller to initiate the 5-minute purge cycle
5. Before installer leaves the site, he/she must ensure that
the heat pump receives signal from the controller and
the "heat up" process has been started (i.e., fan is
spinning, and hot water outlet pipes are hot and have
reached +60°C). If time of day contradicts the option
settings, the system will not run as required. If the
option selected is outside normal time it is
recommended the heat cycle is activated using the
boost function.
26
Reclaim Energy |
Quick Start/Install Manual – v1.0
2.5
POST INSTALLATION
INSPECTION CHECKLIST
A licensed installer should check for the following before
leaving the installation site.
System check: Check all connections for leaks and that all
components are installed, as per this manual.
Take photos of all system components with clear serial
numbers for warranty purposes. This should include
photos of the plumbing lines to and from the tank, heat
pump and sensor port connection.
Note down the Tank Serial Number
Note down the Heat Pump Serial Number
Note down the Controller Serial Number
Fill out the installation record form supplied for system
warranty and service issues.
Submit your Installation Record Form via
Email: warranty@reclaimenergy.com.au
Complete the rebate forms for the system prior to leaving
the site, this will require the installer's signature. Note
these forms are not supplied with us or in this document.
This is responsibility of customer or installer to have the
rebate forms ready to fill out.
For the Remote
Controller, connects
to the RJ45 terminal
on the PCB display
6
6

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rehp-ky-co2-250glRehp-ky-co2-315glRehp-ky-co2-400glReclaim energy rehp-ky-co2-160glReclaim energy rehp-ky-co2-250glReclaim energy rehp-ky-co2-315gl ... Show all

Table of Contents