SETTING UP THE GATE
Note: Wait for the cement to set before starting this operation.
1) Assemble the release levers on the support bracket, and fit
the latter on the pivot in the foundation box, also inserting the
ball supplied (fig. 8).
Note: Grease both the pivot and the ball.
Note: Do not lubricate the release system for any reason.
2) Prepare the guide bracket, as follows:
use a "U" profile with dimensions indicated in fig. 9;
ascertain the correct location of the leaf on the "U" profile
with reference to the axis of rotation (fig. 10 a-b); seal the "U"
profile on the post side with a plate, as shown in fig. 10 a-b.
3) Carefully weld the guide
bracket to the support bracket
(fig. 11).
4) Fit the gate into the guide
bracket and fix the top hinge
in place.
IMPORTANT: To ensure trouble-free
operation, do NOT weld the gate
leaf to the guide bracket or to the
support bracket.
5) Manually verify whether the gate opens and closes completely
and smoothly, stopping at the mechanical travel stops.
5.4

INSTALLING THE OPERATOR

1) Open the gate leaf.
2) Place the operator on the fastening screws on the foundation
box, and fix it by means of the nuts and washers supplied (fig.
13 a-b-c).
Note: In order to determine the exact position of the operator with
the levers for 110° and 140° opening, please refer to fig. 12.
In any case the operator pinion must be on the opposite side of
Fig. 8
leaves opening direction.
Fig. 9
3) Manually close the leaf and fit the driving levers supplied, as
shown in fig. 13 a-b.
levers for 110°
Fig. 10 a
levers for 140°
Fig. 10 b
7
ENGLISH
Fig. 11
Fig. 12
Fig. 13 a
Fig. 13 b

Advertisement

loading

This manual is also suitable for:

RollerRoller 24