4 Installation
4 Installation
4.2

Mounting

Step 1. Install the mounting bracket
DANGER
1 ) Use a
horizontally
10mm in diameter and 60 mm in deep. Refer to Step 1 and Step 2.
2) Knock the expansion screw kit into the hole together with a hammer. Refer to Step 3.
Note: Do not remove the nut unit.
3) After tightening 2-3 buckles, the expansion bolts are tight and not loose, and then unscrew the bolts,
spring washer, gasket. Refer to Step 3.
4) Install the bracket on the wall, the bracket screw is pointed at the expansion tube on the wall, then install
the gasket and tighten screw. Refer to Step 4.
Set bracket horizontally.
Mark the holes position on the wall.
1
Expansion screw group
(M6; 3 sets)
Install the expansion screw
3
1.The walls must be fireproof and non-flammable materials, otherwise there is a fire
risk.
2.Before drilling holes ,check whether there are electric power pipes buried in the
walls to avoid risks.
ruler to mark the position of the 3 holes on the wall. Refer to Step 1. And drill 3 holes,
E D C
B
A & B
C & D & E
Ø: 10mm; Depth: 60mm
Drill the holes.
2
A
M6 Expansion screws; 2.5N·m
4
Install bracket.
11