Finishing the Job
After the Triple Leak and Evacuation (and refrigerant trim charge, if any) procedures have been performed, follow the steps below to open
the refrigerant lines.
1. Verify that the auxiliary service port is removed (if used in the Evacuation procedure) and the original Schrader core was re-installed on
the gas (vapor) suction service port.
2. The service ports are a back-seated type with a right hand thread. Remove the service valve caps on both the gas (vapor) suction and the
liquid service ports.
3. Using an appropriately sized Allen wrench, fully open the valves on both the gas (vapor) suction and the liquid service ports by turning the
valve stem counterclockwise.
4. Turn until the valve stem is out, stops, and the valve is completely backseated.
5. Securely replace service port caps on both the gas (vapor) suction and the liquid using an adjustable wrench.

Test Run

After all installation procedures are complete, the system is ready for a test run. Follow the guidelines below.
1. Verify that the power supply is ±10% of the rated voltage.
WARNING
All power wiring installation must be performed by trained service providers working in accordance with local, state, and NEC regulations related to
electrical equipment and wiring, and following the instructions in this manual. Failure to do so will lead to electric shock and bodily injury or death.
NOTE
All power wiring installation must be performed by trained service providers working in accordance with local, state, and NEC regulations related to
electrical equipment and wiring, and following the instructions in this manual. Failure to do so will lead to property damage and equipment malfunc-
tion.
2. Check that all drain piping, refrigerant piping, and wiring / cables are not damaged and are properly connected. Verify the terminals are
tight. Check the operation of the remote wired controller. Check if the drain piping and refrigerant piping do not have leaks and are fully
and correctly insulated.
3. Check that both the gas (vapor) suction and liquid refrigerant piping service valves are fully open.
4. Turn on the power to the system and the remote wired controller. Switch the system to Test Operation Mode (see Controller Installation
Manuals for details).
5. Test the system in cooling operation first, even if installing in heating season.
WARNING
injury, or death.
NOTE
damage.
6. To cancel the test operation mode, press any button on the wired remote controller.
FINAL INSTALLATION PROCEDURES
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. "LG" is a registered trademark of LG Corp.
Do not apply excessive force.
Test Run
67

Advertisement

Table of Contents
loading

This manual is also suitable for:

Lgred lh248hhv1

Table of Contents