General Site Requirements & Floor Layout - ABB UniGear ZS2 Installation, Operation And Maintainance Instructions

Table of Contents

Advertisement

Lift the CB manually or using a suitable hoist, and
place it on the trolley. Ensure Removal of CB
lifting hook arrangement before inserting
in the panel.
Assembly of the switchgear at site:
In order to obtain an optimum installation
sequence and to ensure high quality standards,
site installation of the switchgear should be
carried out only by specially trained and skilled
personnel, or at least supervised and monitored
by authorized and persons responsible.
Floor layout
LATERAL CLEARANCE
SIDE
600
1000
5.7 General site requirements & floor layout
On commencement of installation on site:
The switchgear-room must be completely
finished
Provided with lighting and electricity supply
Room shall be lockable, dry and with facilities
for ventilation
All the necessary preparations, such as wall
openings, ducts, etc., for laying the power and
control cables up to the switchgear must
already be completed
The ceiling must be high enough for assembly
of pressure relief duct and exhaust duct
Compliance with the conditions for indoor
switchgear according to normal service
conditions as per IEC 62271-1 including the
conditions for the "minus 5 indoor" temperature
class must be ensured.
REAR CLEARANCE
REAR
SIDE
600
1000
1000
FRONT
FRONT CLEARANCE
LATERAL CLEARANCE
Material
27