4 Installation, commissioning

4
Installation, commissioning
4.1

Installation, assembly

The underfeed combustion system may only be assembled and commissioned by qual-
ified Schmid AG energy solutions staff.
It is positioned according to the project-specific installation diagram.
The installation location must be clean and dry at the beginning of the assembly work
(swept clean).
The scope of supply and provisions regarding the services to be provided by the
customer are specified under assembly and commissioning in the order confirmation,
as well as in the general terms and conditions of delivery. The electrical assembly and
installation is not included within the Schmid AG energy solutions scope of supply.
Danger from electrical energy.
An electric shock can cause serious injury!
Please note the connection information. See wiring diagram in the appendix as well as
the nameplate on the combustion grate.
During the installation work the system must not be subjected to a voltage.
Electrical connections must only be performed by specialists.
Defective cables and connectors must be replaced immediately.
Danger of fire resulting from installation on site.
Incorrect floor or wall conditions, or flammable materials in the installation location can
cause a fire hazard.
The firing unit may only be placed on a fireproof surface.
The distances to walls and other structures must be complied with.
There must not be any flammable materials in the combustion chamber or near the
underfeed combustion system.
Fire protection measures as stipulated in local regulations and guidelines must be
complied with.
Higher ground temperatures can occur near the boiler installation site (max. ambient
temperature +60°C).