Critical Power
4.3

RPA PARALLEL SYSTEM OPERATION

4.3.1 Introduction to the RPA Parallel System

Fig. 4.3.1-1 Block diagram RPA Parallel System operation
Two or more equal power units can be paralleled to increase the output power (paralleling for capacity)
or to improve the overall reliability of an UPS system (paralleling for redundancy).
The outputs of parallel units are connected to a common power bus, and in normal operation the units
connected on the parallel bus share the Load equally.
The modular concept of TLE Series allows parallel operation of up to 6 units, without using paralleling
switchgear, external bypass circuits or common control circuitry (see Fig. 4.3.1-1).
Parallel units for power capacity
Several units can be paralleled in order to achieve output power greater than the maximum power of a
single unit.
The maximum total power shared between the paralleled units is equal to the total installed nominal
power.
In the event of a failure of one unit, the power supplied by the UPS system becomes insufficient and the
Load will be transferred to the Utility Bypass source.
Parallel units for redundancy
The nominal power rating of the n out of n+1 redundant paralleled modules must be equal to or higher
than the required Load power.
The Load will be equally shared by the n+1 units connected on the output bus.
Should one of the n+1 paralleled units trip Off-line, the remaining (n) modules will supply the Load,
maintaining conditioned power to the critical Load.
From this results higher reliability and security for the Load plus a higher MTBF (Mean Time Between
Failures).
Modifications reserved
Page 17/92
GE_UPS_USM_TLE_SUL_M62_1M0_2US_V010.docx
User Manual TLE Series 625 - 750 - 1000 UL S2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tle 750 ul s2Tle 1000 ul s2

Table of Contents