Hussmann VR1-D User Manual page 11

Deli service merchandiser
Table of Contents

Advertisement

Installation (cont'd)
Setting
STEP 1. Using case blueprints, measure off and
mark on the floor the exact dimensions of where
the cases will sit. Snap chalk line for front and
back positions of base rail or pedestal. Mark the
location of each joint front and back. Find the
highest point throughout the lineup. FLOORS
ARE NORMALLY NOT LEVEL! Determine the
highest point of the floor; cases will be set off
this point. All cases in the entire lineup must be
brought up to the highest level of the case sitting
at the highest point in the lineup.
ACCESS LOWER BOLT LOCATIONS
BY REMOVING FRONT AND REAR
BODY PANELS
ACCESS UPPER BOLT LOCATIONS BY
REMOVING INNER ARM COVER
STEP 2. Set first case over the highest part of
the floor and adjust legs so that case is level.
STEP 3. Set second case within one foot (1') of
the first case. Keep the supports along the length
of the case and far end of case. Level case to the
first using the instructions in step one.
It is the contractor's responsibility to install
case(s) according to local construction and
health codes.
Do not use bolts to pull cases together.