Burner ignition

Once the above steps are complete, the burner should light.
If the motor starts up, but the flame does not appear and the control
box goes into lockout, reset it and wait for a new ignition attempt.
If ignition is still not achieved, it may be that gas is not reaching the
combustion head within the safety time period of 3 seconds. In this
case increase gas ignition delivery.
The arrival of gas at the pipe coupling is indicated by the U-type
pressure gauge (Fig. 47).
If further burner lockouts occur, refer to the "Release procedure"
given in the equipment manual supplied.
Once the burner has ignited, proceed with the global adjustment of
the burner.
5.7.1
Air / gas adjustment and output modulation
The air/gas regulator and output modulation system equipping RS
series burners performs a number of integrated functions to opti-
mise burner function, in both individual installations and in combi-
nation with other units (e.g. double furnace boiler or multiple heat
generators in parallel).
The basic system functions control:
1
The dosage of the air and fuel through positioning using direct
servocommands of the relevant valves eliminating the possi-
ble play in the calibration systems with mechanical cam lever
mechanisms, used on traditional modulating burners.
2
The modulation of the burner output in accordance with the
load required by the system, with maintenance of the pres-
sure or temperature of the boiler at the operating values set.
3
The sequence (cascade adjustment) of more than one boiler
through the suitable connection of the various units and the
activation of the internal software of the individual systems
(option).
Further interfaces and communication functions with computers,
for remote control or integration in central supervision systems are
available on the basis of the configuration of the system.
The first start up and every further internal setting
operation of the adjustment system or the expan-
sion of the base functions require access by means
of password and are to be carried out by service
WARNING
personnel who are especially trained for the internal
programming of the instrument and the specific ap-
plication created with this burner.
The first start-up and curve synchronisation manual is supplied with
the burner.
At request, the complete manual for the control and setting of all
parameters is available.
20142253
Start-up, calibration and operation of the burner
40
GB

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rlas 800/ev20164299201643002016430120164302

Table of Contents