For a greenhouse length – L 6 and L 7 – 2 pairs of tension braces are installed in each
second field --from the greenhouse gable point of view -
Attention – the tension braces are installed slightly "tense" and must be installed before
the roof glazing is installed, as there is still the possibility to push the greenhouse ridge
slightly upwards so that the last screw can easily be inserted or connected/screwed
together with the tension braces.
{picture}
8. Glazing of the gable peaks
Now it is appropriate to mount the upper glass panels on the gables. Two safe step ladders and
4 hands are required to adjust the triangular panes from the top into the bars at a height of
approx. 2.3 m and screw them in the middle with the cover shells – short version – left/right.
{picture}
9. Mounting of the roof edge bars
The roof edge bar is first inserted into the ridge profile, onto the set panes, and then carefully
inserted into the eaves profile, where it is mounted to the eaves profile just like before.
Attention two screws have to be inserted into the channel of the eaves profile, one M 6 x 55
and one screw M6 x 12, in order to make a connection with the "repair-static strut" M6 x 55 the
stainless steel corner connector. In this area, please check again the alignment of the profiles
with a level and tighten all screws. Check at the corner connector that the eaves edge and
gable crossbar are tightly pushed together!!
{picture}
10. Inserting the roof glazing
For additional sealing, silicone plug-in gaskets, length 820 mm (already pre-cut) are used on
the eaves profiles, which later touches the bottom of the ISO safety glass panes of the roof.
They provide additional insulation and separation of the condensation water channel located
on the inside.
{picture}
Now the ISO safety glass panes can be slid in from the side of the greenhouse.