"Genie" is a Registered Trademark of "QED Environmental Systems" "SPG" is a Registered Trademark of "QED Environmental Systems" The QED Environmental Systems logo is a Registered Trademark of "QED Environmental Systems" QED Environmental Systems is a Registered Trademark of "QED Environmental Systems"...
Table of Contents AP-2 Manual Table of Contents Introduction_________________________________________________1 Safety ......................1 How to Contact QED................2 Chapter 1: Safety ____________________________________________3 A Partial List of Safety Procedures ............3 Fire and Explosion Protection ..............4 Personal Protection ................... 4 Spill Protection ..................4 Chapter 2: Overview _________________________________________5 General Specifications ................
Page 4
AP-2 Manual QED Environmental Systems Chapter 3: Equipment________________________________________12 Unpacking....................12 Equipment List..................12 Tools......................13 Parts List ....................13 AP-2 AutoPumps ..................13 Bottom-Loading AP-2/BL ..............13 Top-Loading AP-2/TL ..............13 Specifications..................16 Component Materials ................16 Performance and Air Use Curves ............16 Landfill Pump Configurations ............
Page 5
Table of Contents AP-2 Manual Chapter 5: Start Up and Operation _____________________________36 Start Up Checklist..................36 Adjusting the Pump Cycle Counter ............37 Observation of System Operation............. 38 Downwell Testing of the AutoPump............38 AutoPump Shutdown while Submerged........... 38 AutoPump Removal Technique (optional) ..........39 Chapter 6: Maintenance ______________________________________40 General Maintenance ................
Page 6
AP-2 Manual QED Environmental Systems Appendix A: Performance Curves_______________________________60 Appendix B: Air Consumption Curves ___________________________66 Appendix C: AP-2 Conversions _________________________________72 Appendix D: Vacuum on Well __________________________________75 Appendix E: Air Compressor __________________________________80 Installation ....................80 Electrical Wiring for the Compressor..........81 Motor Overload Protection..............
Page 7
Table of Contents AP-2 Manual Figures: Figure 1 - How it Works..................7 Figure 2 - Overview of the AutoPump System ..........9 Figure 3 - Long and Short Bottom-Loading (AP-2/BL)........14 Figure 4 - Long and Short Top-Loading (AP-2/TL) .......... 15 Figure 5 - Long and Short AP-2 Bottom Loading with Leachate Screen..
Page 8
AP-2 Manual QED Environmental Systems Figure 23 -Short AP-2/TL Performance Curves: 1/2-inch (13 mm) I.D. Discharge US and METRIC UNITS .... 65 Figure 24 - Long AP-2/BL Air Consumption Curves: 1/2-inch (13 mm) I.D. Discharge US and METRIC UNITS .... 68 Figure 25 - Long AP-2/TL Air Consumption Curves: 1/2-inch (13 mm) I.D.
We wrote this manual so it can be easily understood by users who may not be familiar with systems of this type or are using a QED system for the first time. Safety Safety has been a cornerstone of our design which has been proven out in building and shipping systems throughout the world.
If for any reason you are unable to find what you need in this manual please feel free to contact the QED Service Department at any time. We encourage you to use following communication methods to reach us at any time:...
These safety procedures should be followed at all times when operating QED equipment on or off site, and should be considered as warnings: • Wear safety goggles when working with the AutoPump System to protect eyes from any splashing or pressure release.
The AutoPump System minimizes the potential for accidents with the following safeguards: Fire and Explosion Protection Almost all of QED underground fluid extraction systems are pneumatic. This offers many inherent fire and explosion protection features: • Compressed air lines eliminates electrical wiring in hazardous areas.
AP-2 Manual Chapter 2: Overview The AutoPump ® fills and empties automatically, and is very easy to install, use, and maintain. The AutoPump is a pneumatic fluid extraction pump that pumps in pulses. It handles any liquid which flows freely into the pump and is compatible with the component materials and with the connecting hoses.
AP-2 Manual QED Environmental Systems This is How it Works The AutoPump is a submersible compressed air-driven pump which fills and empties automatically. It also controls the fluid level in a well automatically. The pump fills (see Figure 1) when fluids enter either the top or bottom check valve. Air in the pump chamber exits through the exhaust valve as the fluid fills the pump.
Page 15
AP-2 Manual Chapter 2: Overview Figure 1 - How it Works Revision 7 - August, 2007 Page 7...
• The AP-2 can be configured to fill from the top or the bottom. Figure 2 on the next page illustrates an overview of an AutoPump System. The AP-2 System provides everything required for pumping fluid from a well. QED can also supply the air compressor, if desired.
Page 17
AP-2 Manual Chapter 2: Overview Figure 2 - Overview of the AutoPump System Revision 7 - August, 2007 Page 9...
(See Appendix D) Abrasive particles in the well Please contact QED service if you encounter problems with abrasives in the well. Hard pipe air supply connection to the pump These can cause debris and scale to travel down to the pump. It can also prevent the pump from cycling smoothly due to a solid connection (non-flexing) to the top of the pump.
AP-2 Manual Chapter 2: Overview Options and Accessories The following options and accessories are available from QED. Contact your QED Representative regarding the following: • AP Data Module – This water-resistant enclosure protects and shields surface instrumentation from weather and/or harsh site conditions while providing easy visual access to key system instrumentation readings.
AP-2 Manual QED Environmental Systems Chapter 3: Equipment Unpacking During the unpacking procedure, check for the following: • All parts on the packing list have been included in the box • All fitting openings are unobstructed • The equipment has not been damaged in shipment...
AP-2 Manual Chapter 3: Equipment 5. Pump support system: • Well cap • Polypropylene support rope with quick-link assembly or SS wire rope Tools The following tools are used to service the AP-2: • Spanner wrench • 3/32-inch Hex (Allen) key •...
Page 22
AP-2 Manual QED Environmental Systems Figure 3 - Long and Short Bottom-Loading (AP-2/BL) Page 14...
Page 23
AP-2 Manual Chapter 3: Equipment Figure 4 - Long and Short Top-Loading (AP-2/TL) Revision 7 - August, 2007 Page 15...
AP-2 Manual QED Environmental Systems Specifications Outside Pump Length Vol/Cycle Range Weight Diameter 55-inches 0.14 gal - 0.17 gal 7.8 lb 1.75-in Long AP-2/BL 139-cm .53 L - .64 L 3.6 kg 4.45-cm 33-inches 0.05 gal - 0.08 gal 5.4 lb 1.75-in...
Page 25
AP-2 Manual Chapter 3: Equipment Figure 5 - Long and Short AP-2 Bottom Loading with Leachate Screen Revision 7 - August, 2007 Page 17...
AP-2 Manual QED Environmental Systems Single Stage Filter/Regulator A single stage 5 micron particulate air filter/regulator has an a manual or an optional automatic drain and is installed on the system air supply hose. The filter/regulator removes particles and some oil vapor, and water droplets from the air passing to the AP-2. The regulator should produce at least as much pressure as required to move the fluid from the depth at which the pump is installed.
* Nylon tubing is available in single tube or jacketed bundles. Contact QED for the sizes and bundle configurations. If optional quick-connects are used, the flow of air and fluid in the hoses runs into the male plug and out of the female socket.
AP-2 Manual QED Environmental Systems Pump Cycle Counter Refer to Appendix F – Pump Cycle Counter Volumes Pumped Per Cycle • The volume of fluid pumped per cycle from an AutoPump varies depending upon the inlet air pressure, the fluid inlet head and the force against which the pump must move the fluid.
AP-2 Manual Chapter 3: Equipment Pump Support System To safely support the AP-2, a pump support system is offered. Included in the system are a well cap, support rope, and quick-link assembly. (See Figure 12 on page 33, and Figure 13 on page 34) Well caps with various fitting combinations are available.
AP-2 Manual QED Environmental Systems Chapter 4: Assembly & Installation WARNING: PVC pipe is generally not recommended for compressed air service. Cautions The following suggestions are offered to reduce the complications involved in assembly and installation. • Cover the hose ends with tape if they are being pulled through trenches. Be sure the ends of the hoses that connect to the air compressor and fluid discharge have the correct fitting leading out of the well.
AP-2 Manual Chapter 4: Assembly & Installation Compressed Air Supply The AP-2 System includes a compressor-to-pump air line quick disconnect fitting for the compressor. There is a distinct air inlet on the AP-2; an “IN” is stamped next to it on the head of the pump.
Page 32
AP-2 Manual QED Environmental Systems Figure 7 - Locking Quick-Connects Page 24...
AP-2 Manual QED Environmental Systems STEP Attach AutoPump Air Hose (green) a. If a Pump Cycle Counter (PCC) is used, install it downstream of the air filter regulator and as close to the pump as is reasonable. b. Attach the AutoPump air hose to the single stage filter/regulator or optional Pump Cycle Counter (See Figure 2 on page 9) Attach the other end of the AutoPump air hose to the AutoPump.
AP-2 Manual Chapter 4: Assembly & Installation STEP Tip the top of the pump downwards to about 45°. The float should slide to the top of the pump and open the air valve. Air should be heard going into the pump. It will exit the inlet fluid check valve (Bottom-loading) or the outlet check valve (Top-loading).
Page 38
AP-2 Manual QED Environmental Systems Figure 11 - Examples of Well Caps Page 30...
Page 39
AP-2 Manual Chapter 4: Assembly & Installation Hose bundling or the use of jacketed tubing reduces equipment entanglement at the well surface, and aids the removal of the pump from the well. Bundling also assists in positioning the pump and down-well hose assembly against one side of the well casing. Maximum space is created for other items, such as probes, to be periodically placed inside the well.
Page 40
AP-2 Manual QED Environmental Systems Figure 12 - Hose Bundling: Part 1 of 2 Page 32...
AP-2 Manual QED Environmental Systems STEP Continue to alternate the air exhaust and the air supply tie-wraps every two feet, stopping about five feet from the wellhead. STEP Being careful not to leave any sharp edges, cut the excess from the tie- wraps.
Page 43
AP-2 Manual Chapter 4: Assembly & Installation The pump rate can be increased slightly by increasing the air pressure to the pump. However, under conditions with high inlet pressures and little discharge resistance, some air may exit with the fluid. That would be due to a brief residual pressure in the pump which discharges fluid (and air) even after the exhaust valve is opened.
AP-2 Manual QED Environmental Systems Chapter 5: Start Up and Operation Start Up Checklist In normal operation, the AutoPump System requires little attention. Before regulating the air pressure to the desired operating pressure, ensure that the following conditions exist: 1. Personal Protective Equipment (PPE) is being used by all personnel.
AP-2 Manual QED Environmental Systems Observation of System Operation Observe the system operation for at least 10 pump cycles to ensure everything is working. If the well influx is low so the pump seldom cycles, pour clean water into the well to check on the pump.
AP-2 Manual Chapter 5: Start Up and Operation AutoPump Removal Technique (optional) By pressurizing the exhaust hose as noted above and airlifting the fluids out of the well, the fluid in an AutoPump and discharge hose can be reduced significantly. This can be used to lighten the system before removing it from the well.
AP-2 Manual QED Environmental Systems Chapter 6: Maintenance General Maintenance The AutoPump should be relatively free of maintenance. The frequency of maintenance depends upon the nature of the fluids being pumped. Follow these general maintenance checks. • Periodically inspect all hoses and connections for damage. Make sure that the hoses are not split or cracked, and listen for leaks in the system.
AP-2 Manual Chapter 6: Maintenance Maintenance Table A visual check and/or maintenance is recommended at least once every two weeks, but some site environments may demand more frequent service. The following table outlines the recommended minimum schedule for the AP-2 System. Equipment Biweekly Monthly*...
Page 50
Hand tighten the element after replacing it. Make sure to replace the correct filter element. Blue or black filter bowl: QED Filter element Part No. 205071 Silver filter bowl: QED Filter element Part No. 205800 STEP...
AP-2 Manual Chapter 6: Maintenance AutoPump Service AutoPump Shutdown and Removal from Well To shut down and remove the AutoPump, follow these directions: STEP Wait until the pump is in its discharge cycle and then raise it above the water level in the well. This will empty most of the fluid from the pump making it lighter to lift.
AP-2 Manual QED Environmental Systems STEP 1 - Insert and hold a spanner wrench on the circumference of the lower head. Rotate a spanner wrench counterclockwise on the lower head assembly. Hold the casing with a handle or a strap wrench. (See Figure 14) Caution: Do not leverage any tool against the air inlet or air exhaust fittings.
AP-2 Manual Chapter 6: Maintenance Iron Build-up Cleaning Procedure After the casing has been removed from the AutoPump please follow the procedure below: Note: The procedure described below can be seen in the Maintenance Video Tape. This will aid the technicians understanding and ease of properly disassembling the AutoPump, effectively cleaning components and then re-assembling the AutoPump.
AP-2 Manual QED Environmental Systems STEP The Control rod (See Figures 15 through 18) is the next component to be cleaned. Only use a Scotch Brite pad for removing any iron or degris on this metal alloy control rod. STEP The final component to be cleaned is the outer AutoPump casing.
AP-2 Manual Chapter 6: Maintenance STEP Using a spanner wrench on the bottom fitting, or, a strap wrench on the bottom end of the casing (pump bottom), turn the parts together until the casing just contacts the pump head. STEP Turn the bottom check valve or the plug in the reverse direction (counter clockwise) so it is looser by 1/4 turn.
Chapter 7: Troubleshooting & Repairs Problems may occur and usually can be easily resolved by following these instructions. If, after careful reading and service, you cannot resolve the problem, please contact the QED Environmental Systems (QED) Service Department at (800) 537-1767.
AP-2 Manual Chapter 6: Maintenance Troubleshooting 1. Air Supply: • If the air pressure is too low, or if the flow is severely restricted, the pump will not cycle. Check the flow by inserting the pump air fitting part way into the air line socket.
Page 64
Determine if any part of the float foam itself can contact the discharge pipe. Move each end of the float back and forth, sideways, to ensure that the pins on the plate of the float prevent float foam contact with the pipe. Call QED for repair options. Note: If viscous materials cause continual problems, contact QED for possible solutions.
Page 65
AP-2 Manual Chapter 7: Troubleshooting & Repair 8. Fluid Check Valves: • Open the pump. Hold the pump vertically and pour water into the discharge check valve. If water flows through, clean the valve. • The valve assembly may be soaked in a solvent. Be careful to not damage the teflon ball with the tools used for cleaning.
AP-2 Manual QED Environmental Systems Returning Equipment for Service If the equipment needs to be returned to QED for servicing, please follow these steps: STEP Call the QED Service Department and obtain a Return Material Authorization (RMA) number. Please have available the customers contact person’s name, company name and address, phone number, fax...
AP-2 Manual Chapter 7: Troubleshooting & Repair Equipment Cleaning Requirements If the equipment is to be shipped to another site or to the factory for service, it needs to be thoroughly cleaned before leaving the site. Cleaning the equipment protects the user (sender), the shipper, and the receiver from dirt and/or contaminants.
AP-2 Manual QED Environmental Systems Appendix A: Performance Curves These curves were derived from in-house tests using a pump with average air flow capacity. Flow rates in the field may vary slightly due to temperature, air quality, flow restrictions and minor differences in pump adjustments.
Page 69
AP-2 Manual Appendix A: Performance Curves With the previous information, obtain the flow rate by using the following steps: • On the horizontal scale, find the depth in the well at which the pump will be located. • Trace that depth upwards to the line for the air inlet pressure you selected. •...
Page 70
AP-2 Manual QED Environmental Systems Figure 20 - Long AP-2/BL Performance Curves: 1/2-inch (13 mm) I.D. Discharge US and METRIC UNITS Page 62...
Page 71
AP-2 Manual Appendix A: Performance Curves Figure 21 - Long AP-2/TL Performance Curves: 1/2-inch (13 mm) I.D. Discharge US and METRIC UNITS Revision 7 – August, 2007 Page 63...
Page 72
AP-2 Manual QED Environmental Systems Figure 22 - Short AP-2/BL Performance Curves: 1/2-inch (13 mm) I.D. Discharge US and METRIC UNITS Page 64...
AP-2 Manual QED Environmental Systems Appendix B: Air Consumption Curves The following charts show the air consumption curves for the Long and Short length AP-2 AutoPumps. These curves can be used to estimate air use and compressor sizing. A compressor with reserve capacity is recommended.
Page 75
AP-2 Manual Appendix B: Air Consumption Curves If the yield of the well is less than the maximum pump rate predicted by the appropriate flow rate graph, multiply the actual fluid recovery rate times the air use factor. This air use can be diminished if the regulator pressure is reduced.
AP-2 Manual QED Environmental Systems Appendix C: AP-2 Conversions The AP-2 can be converted the from Top- to Bottom-Loading or Bottom- to Top- Loading by rearranging the check valves. For Bottom-Loading to a Top-Loading conversion, see Figure 28 on the next page.
AP-2 Manual Appendix D: Vacuum on Well Appendix D: Vacuum on Well The AP-2 will work in a well that is under vacuum, but there are several conditions that must be considered. These conditions are described in Figure 30, Figure 31, Figure 32, and Figure 33 on the following pages.
Compressors start and stop automatically. Do not place hands or objects on or near any part of the compressor. QED Environmental Systems (QED) does not usually supply the air compressor. It is best to buy the compressor from a local supplier who provides service. Follow the instructions that accompany the compressor.
AP-2 Manual Appendix E: Air Compressor Note: The information on compressors is for reciprocating piston compressors. A centrifugal compressor produces about twice the air of a piston compressor for the same horsepower. • As a general rule, a piston-type compressor should not start more than six times per hour. Also, a piston compressor should not operate more than 50% of the time.
This will help to extend air filter cartridge life. • Do not lubricate the compressed air coming out of the compressor. QED equipment is designed to run without the aid of lubricated air. The air filters are designed to remove oil from the compressed air.
AP-2 Manual Appendix E: Air Compressor Maintenance Although QED usually does not supply the compressor, this section is provided to help the operator. If the system receives clean, oil-free air from the compressor, maintenance will be significantly reduced. Inspection - Check for possible damage in transit. Almost all compressors are shipped with the flywheel unmounted.
These notes are included as a general guide only. Troubleshooting Although QED usually does not supply the compressor, this section is provided to help the operator. If the system receives clean, oil-free air from the compressor, maintenance will be significantly reduced.
Page 93
AP-2 Manual Appendix E: Air Compressor E. Oil leaks: check and tighten all bolts and nuts to manufacturer’s specifications. Replace gaskets if necessary. F. See “Overheating.” III. Problem: Overheating Solutions: A. Pump running backwards: reverse rotation. B. Inadequate ventilation or high ambient temperature: move intakes to outside and install filters to protect against weather and foreign objects.
Appendix F: Pump Cycle Counter Introduction QED Environmental Systems (QED) Pump Cycle Counters (PCC) are air pulse detecting units that are placed in-line between a pump and its air supply. They require no external power source. A digital readout displays the number of times a pump cycles. PCCs consist of a magnet housing, an internally located magnet shuttle, and a digital display.
Appendix F: Pump Cycle Counter Pump Cycle Counter Operation/Installation When a pneumatically operated pump such as the QED AutoPump® has filled, it triggers itself “On”. This allows air to flow to the pump until a certain volume of fluid has discharged. The air stops; the pump fills; then the cycle continues to repeat.
AP-2 Manual QED Environmental Systems Magnet Housing The magnet housing has the following features: • A clear mark on the outside that indicates the correct direction of air flow. • It is made of anodized aluminum. • It has a 1/4-inch FNPT inlet and a 3/8-inch or 1/4-inch FNPT outlet.
AP-2 Manual Appendix F: Pump Cycle Counter Materials of Construction QED PCCs are made of the following: • Anodized Aluminum • Brass • Stainless Steel • Viton • Engineering Plastics Pump Cycle Counter Weight - 0.4 lbs (0.2 kg) Adjusting the Pump Cycle Counter...
AP-2 Manual QED Environmental Systems Cleaning the Pump Cycle Counter Sometimes the PCC does not count due to either the magnet shuttle or the spring hanging up inside the magnet housing. The counter components can be cleaned by gently washing the unit in warm water.
AP-2 Manual QED Environmental Systems Assembly of the Digital Display (Figure 36) Should the digital display be removed and disassembled for any reason, the procedure for assembling is as follows: STEP Seat the digital display (item #4) on the flat of the display seat (item #5).
AP-2 Manual Appendix F: Pump Cycle Counter AP-2 Volumes Pumped Per Cycle The volume of fluid pumped per cycle from an AutoPump® varies depending upon the inlet air pressure and the total developed head (TDH) (static plus dynamic head). The closer the pressures are to each other, (the TDH is almost the same as the inlet air pressure), the closer the volume pumped per cycle will be to the lower end of the gallon range in the table below.
All warranty durations are calculated from the original date of purchase—determined as beginning the date of shipment from QED facilities and the date QED is notified of a warranty claim. This warranty shall be limited to the duration and conditions set forth below.
Page 105
QED service personnel (unless such repair by others is made with the written consent of QED); resold to other parties; and/or moved to or used on a remediation site other than originally specified.
Page 106
QED shall not in any event be liable for the cost of any labor expended on any such product or material or for any special, direct, indirect or consequential damages to any one by reason of the fact that it shall have been deemed defective or a breach of said warranty.
Page 107
The original purchaser’s sole responsibility in the instance of a warranty claim shall be to notify QED or its appointed agent, of the defect, malfunction, or other manner in which the terms of this warranty are believed to be violated. The purchaser may...
Page 108
QED, or its appointed agent, for determination of warranty coverage. If the return of a component is determined to be necessary, QED, or its appointed agent, will authorize the return of the component at Purchasers expense. If the product proves not to be defective within the terms of this warranty, then all costs and expenses in connection with the processing of the Purchaser’s claim and all costs...
Need help?
Do you have a question about the AutoPump AP-2 and is the answer not in the manual?
Questions and answers