Tools
▶ The tools required for installation and assembly are not
included in the scope of delivery.
Use appropriate, functional and safe tools.
●
1. Ensure the product is suitable for the relevant application.
2. Check the technical data of the product and the materials.
3. Keep appropriate tools ready.
4. Wear appropriate protective gear, as specified in the plant
operator's guidelines.
5. Observe appropriate regulations for connections.
6. Have installation work carried out by trained personnel.
7. Shut off plant or plant component.
8. Secure plant or plant component against recommission-
ing.
9. Depressurize the plant or plant component.
10. Completely drain the plant (or plant component) and let it
cool down until the temperature is below the media vapor-
ization temperature and cannot cause scalding.
11. Correctly decontaminate, rinse and ventilate the plant or
plant component.
12. Lay piping so that the product is protected against trans-
verse and bending forces, and also from vibrations and
tension.
13. Only install the product between matching aligned pipes
(see chapters below).
14. Please note the flow direction (see chapter "Flow direc-
tion").
15. Please note the installation position (see chapter "Installa-
tion position").
www.gemu-group.com
NOTICE
10.2 Flow direction
The flow direction is stated on the product by means of an ar-
row.
Fig. 2: Flow direction of control function 1 (NC)
Fig. 3: Flow direction of control function 2 (NO)
10.3 Installation position
The installation position of the product is optional.
17 / 29
10 Installation in piping
GEMÜ M75