Lighting panelboards - branch circuit monitoring

Advertisement

A S P M E T E R S P L I T C O R E
ASPMETER split core
11. Connect 2-wire 90–277 V AC power to main power
terminals. Observe polarity. For the ASPMETER-A
and ASPMETER-B, connect voltage lines to the voltage
taps (Figure 15). Equip voltage lines with fuses.
Figure 15.
V2/N
90-277 VAC
V1
V1
Line to line (L-L) voltage: 150 to 480 V AC
Line to neutral (L-N) voltage: 90 to 277 V AC
V
V3
N
L - L
L - N
Recommended accessories
Catalog number
ASPCT0
ASPCT1
ASPCT2
25
Description
Six-pack 50 A CT, 6 ft. (1.8 m) lead
Six-pack 100 A CT, 6 ft. (1.8 m) lead
Single 200 A CT, 6 ft. (1.8 m) lead