Preparations for Installation

The installation must comply with national and local regulations and standards applicable to
flame detectors (e.g., NFPA 72) and all local and common engineering practices. It is
recommended to consult with the authority having jurisdiction.
Prior to installation:
Make sure that you have all the components and tools required to complete the
installation before starting. In cases where you cannot complete the installation in a
single session, secure and seal the detectors and conduits before leaving site
Use color-coded conductors or suitable wire markings or labels for the wiring. You may
use 14 to 17 AWG (2.5mm
selection of wire gauge should be based on the number of detectors used on the same
line and the distance from the control unit, in compliance with specifications.
Individually screen twisted pair cable is recommended for RS485 terminals.
Use suitably rating wire for the application certification and temperatures.

Required Tools

The detector can be installed using the following tools:
Hex. KEY 6 mm
Hex. KEY 10 mm
Wrench 13 mm
Flat Screwdriver 6 mm
Flat screwdriver 3.5mm

Certification Instructions

Warnings
Do not open the detector, even when isolated, when flammable atmosphere present.
The equipment may be used in hazardous areas with flammable gasses and vapors with
apparatus groups IIC, IIB and IIA and with temperature classes T1, T2, T3, T4 and T5. See
details of the explosion proof approvals in section 0.
The equipment is certified for use in ambient temperatures in the range of -67°F to
+167°F (-55°C to +75°C) or -67°F to +185°F (-55°C to +85°C) and should not be used in
temperatures outside this range.
Installation shall be carried out in accordance with the applicable code of practice by
suitably trained personnel.
Inspection and maintenance of this equipment shall be carried out by suitably trained
personnel in accordance with the applicable code of practice.
For more information & technical support: (+1) 714-671-8500 · support@fg-detection.com
2
2
to 1.0mm
) multi-strand wires for the site wiring. The
Tool
Vertical alignment
Horizontal alignment
Mounting the detector
Ground screw connection
Terminal connection
F140V0020.07
Function
10