General:
• All of the location requirements for the
charging station in the " Installation manual"
must be adhered to!
• When mounting the pedestals in parking spaces
or parking garages, appropriate anti-collision
protection must be provided by the customer.
Concrete foundation:
• The calculation, design and manufacture of the
concrete foundation lies in the scope of
responsibility of the producer of the site.
• A horizontal, level and sound foundation is
required for installation.
To ensure safe and permanent anchoring, we
No
Yes
Electrical hazard!
The back-to-back pedestal must always be fitted
with two charging stations!
recommend creating a concrete foundation:
70 cm (L) × 60 cm (W), depth = 50 cm.
Concrete: C30/37
• The base must permit the running off of any
water that has entered the base.
• All cables must be laid precisely in the centre of
the concrete foundation from the base and
must have an excess length of approx. 1.5 m for
the remaining installation activities.
• During the production of the concrete
foundation, the cables must be protected
against damage using appropriate measures
(e.g., a protective tube). The protective tube
must have an excess length of approx. 25 cm
above the concrete foundation.
• Mounting the pedestal on asphalt is not
allowed!