Optional) Connecting The Power Grid Scheduling Signal Cable - Huawei SUN2000-50KTL-ZHM3 User Manual

Hide thumbs Also See for SUN2000-50KTL-ZHM3:
Table of Contents

Advertisement

SUN2000-(50KTL-ZHM3, 50KTL-M3)
User Manual
Figure 5-25 Connecting the cable
Step 2 Connect the signal cable connector to the COM port.
Figure 5-26 Securing the signal cable connector
----End
5.7.4 (Optional) Connecting the Power Grid Scheduling Signal
Cable
Procedure
Step 1 Connect the signal cable to the signal cable connector.
Issue 03 (2022-08-30)
Copyright © Huawei Technologies Co., Ltd.
5 Electrical Connections
48

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-50ktl-m3Sun200050ktl-zhm3-50ktl-m301075485-058

Table of Contents