6.1 Checking Before Power-On

Table 6-1 Checklist
No.
1
2
3
4
5
6
7
8
9
Issue 03 (2022-08-30)
Check Item
SUN2000 installation
Smart Dongle
Cable routing
Cable ties
Reliable grounding
Switch
Cable connection
Unused terminals and ports
Installation environment
Copyright © Huawei Technologies Co., Ltd.
6

Commissioning

Acceptance Criteria
The SUN2000 is installed correctly and
securely.
The Smart Dongle is installed correctly
and securely.
The cables are routed properly as
required by the customer.
Cable ties are evenly distributed and no
burr exists.
The PE cable is connected correctly and
securely.
DC switches and all the switches
connecting to the SUN2000 are OFF.
The AC output power cable, and DC
input power cables are connected
correctly and securely.
Unused terminals and ports are locked
by watertight caps.
The installation space is proper, and
the installation environment is clean
and tidy.
6 Commissioning
50

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-50ktl-m3Sun200050ktl-zhm3-50ktl-m301075485-058

Table of Contents