8.6.1
Preparing the existing battery system
As a first step, the battery modules are required to be charged to a SOC of 100%. They are then discharged to a SOC of 50%.
This ensures that they have a defined SOC value matching the standard delivery SOC of the expansion module(s). The time
required for this process step is approx. 2-3 hours, depending on the initial state of charge.
The first step can be started by the end consumer thus avoiding idle time for the installer on site.
Step
Description
1
Launch the"RCT Power APP" and establish connection to the
inverter.
2
Press the settings icon"
3
Tap on "LOGIN" Enter the password in the dialogue box and
press "OK" to enter the configuration options screen.
(Login Customer Area, password: "********")
4
Select "MAINTENANCE AND TEST" and then "BATTERY
EXTENSION".
".