Periodic Maintenance
Contractor Confi rmation Check Sheet
This check sheet must be completed by the installing contractor and submitted prior to requesting Trane Service
start-up support. The check sheet identifi es a list of items that need to be completed prior to actual machine start-up.
Addressed to the Trane Service offi ce of:
Job Name:
Model No.:
Unit
❏ Unit installed
❏ Isolator pads in place
Chilled Water
❏ Connected to the unit
❏ Connected to the air handling units
❏ Connected to the pumps
❏ System fl ushed and then fi lled
❏ Pumps run and air bled
❏ Strainers cleaned
❏ Flow switch installed and checked/set
❏ Throttling cock installed in leaving water
❏ Thermometers installed in leaving/entering water
❏ Gauges installed in leaving/entering water
We will therefore require your service technician on job by*_____________________.
Checklist completed by____________________________________________________.
Date____________________________________________________________________.
* Return this completed checklist to your Trane Service offi ce as soon as possible to enable the start-up visit to
be scheduled. Be aware that advance notifi cation is required to allow scheduling of the start-up as close to the
requested date as possible. Additional time required to complete the start-up and adjustment due to incompleteness
of the installation will be invoiced at prevailing rates.
40
Contractor Confi rmation Check Sheet
Job location:
Sales order No.:
Cooling water
❏ Connected to the unit
❏ Connected to the cooling device
❏ Connected to the pumps
❏ System fl ushed and then fi lled
❏ Pumps run and air bled
❏ Strainers cleaned
❏ Flow switch installed and checked/set
❏ Throttling cock installed in leaving water
❏ Thermometers installed in leaving/entering water
❏ Gauges installed in leaving/entering water
❏ Cooling water control operational
❏ Water treatment equipment
Wiring
❏ Power supply connected and available
❏ External interlock connected
Load
❏ System can be operated under load condition
RLC-SVX023B-GB