Download Print this page

JLG LT3 Operation And Safety Manual page 21

Lighting tower

Advertisement

1.6
1.6.1 MOVING THE LIGHTING TOWER
BY FORKLIFT / TELEHANDLER
Figure 1.6.1
Forklifting Procedure
!
WHEN USING A FORKLIFT TO MOVE
THE LIGHTING TOWER USE ONLY THE
FORKLIFT
TYNE
FORM THE LIGHTING TOWER'S BASE.
Prior to using a forklift/telehandler to move
a lighting tower, ensure that the mast is
lowered to the stowed position, the
lighthead and LED lights are horizontal
when stowed, and the genset is shut
down.
The JLG LT
3
's maximum mass: 1000 kg
Each side of the lighting tower base has
two fork pockets. Use a forklift of adequate
capacity to lift and move the lighting tower.
Before lifting and moving the lighting tower,
ensure both forklift tynes protrude at least
800 mm into the fork pockets.
Fork pocket opening: 90 mm x 190 mm
Fork pocket centres: 680 mm
680
1001281353
Oshkosh Corporation Classification ‐ Restricted 
LIFTING & TRANSPORTING
JLG LT
POCKETS
THAT
JLG Industries (Australia) Pty Ltd
Oshkosh Corporation
3
1.6.2
CRANING THE LIGHTING
Craning Procedure
!
USE THE LIFTING POINT PROVIDED
ON THE MAST TO LIFT THE LIGHTING
TOWER WITH A CRANE. DO NOT LIFT
FROM ANY TIE-DOWN LUG. DOING SO
WILL DAMAGE THE LIGHTING TOWER
AND POSSIBLY INJURE PERSONNEL.
The mast and lights should be in the
stowed position and the engine generator
shut down prior to lifting the machine
Ensure all outrigger legs are fully retracted
and locked in the stowed position.
Using suitable lifting equipment attached
to the mast section one (MS1) lifting lug
proceed to lift the machine as per the
lifting crane's instructions
Figure 1.6.2
TOWER
Page 1-21
28JUL22